Bill of quantities v Schedule of rates
Contents |
[edit] Introduction
This article explains the difference between a bill of quantities (BoQ) or a schedule of rates on construction projects. Both can be used to obtain prices from contractors and for valuing variations. The decision about whether to use a bill of quantities or a schedule of rates depends on the nature of the project as well as the chosen procurement route.
[edit] What is a bill of quantities?
A bill of quantities is a document prepared by the cost consultant (often a quantity surveyor) that provides project specific measured quantities of the items of work identified by the drawings and specifications in the tender documentation.
The bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
The contractor tenders against the bill of quantities, stating their price for each item. This priced bill of quantities constitutes the tenderer's offer.
Typically a bill of quantities will be appropriate on projects that have been designed in detail, and so the precise quantities required are known.
For more information see: Bill of quantities.
[edit] What is a schedule of rates?
A schedule of rates is a list in a contract setting out the staff, labour and plant hire rates that the contractor will use for pricing cost reimbursable instructed daywork. It does not contain any quantities for the specific work items and is typically used when the nature of work required is known but it cannot be quantified, or if continuity of programme cannot be determined.
On a much larger scale, a similar process might be used on a 'schedule of rates term contract', 'term contract' or 'measured term contract'. Tenderers quote unit rates against a document that is intended to cover all likely activities that might form part of the works. As the extent of the work is unknown, the unit rates include overheads and profit. General preliminaries such as scaffolding, temporary power, supervision and temporary accommodation will also have rates. On projects longer than around 18 months there might be escalation provisions based on annual percentage increases.
For more information see: Schedule of rates.
[edit] Summary
In summary, a bill of quantities will typically be used when a detailed design has been prepared and precise quantities can be calculated, whereas a schedule of rates will be used when quantities cannot be determined.
[edit] Related articles on Designing Buildings
Featured articles and news
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.