Punch list
A punch list (also known as a snagging list) is a document that is prepared close to the end of a construction project and issued by the appropriate certifying authority (typically, the architect, contract administrator or employer’s agent). It lists any faults that are identified or works that do not conform to the specifications, which should be rectified prior to a certificate of practical completion being issued.
Generally, snagging refers to a process that takes place a fortnight or so prior to practical completion when an area is considered complete by a contractor and is offered ready for inspection. It is a slang expression widely used in the construction industry to define the process of inspection necessary to compile a list of minor defects or omissions (snages) in building works for the contractor to rectify.
For more information, see Snagging.
This differs from a work-to-complete list which is compiled by a contractor and issued to each subcontractor and their crews at, or near, completion - a list of the remaining items and any defective work that subcontractors are required to complete before leaving the site.
For more information, see Work-to-complete list.
The process of inspection and going through a punch list is usually performed close to the end, if not right at the end, of construction so that the work as a whole can be reviewed and checked. The list of items to be completed or corrected is compiled by the contractor and submitted to the employer’s agent or designer (usually the architect or engineer). Lists tend to be organised either by room or by trade.
Following this, the work is inspected by the agent (sometimes along with the contractor, subcontractor, owner, and any other relevant stakeholders) to determine whether the items on the list have been resolved. Traditionally, the list would be worked through and a hole punched in the margin to indicate that the particular item of work had been completed, hence the term ‘punch list’. Today, digital software is capable of producing virtual punch lists with applications that can be operated via mobile devices as well as more complex web and desktop varieties.
Typical examples of punch list items include: repairing broken windows, replacing missing roof tiles, repainting chipped paintwork, filling cracks, and so on.
Once the list of items has been completed according to the specifications in the contract, or a mutually agreed resolution has been decided upon for certain items, practical completion can be certified.
Following practical completion, there is generally a defects liability period, during which the contractor may be recalled to rectify defects which appear. This is not a chance to correct snagging items apparent at practical completion, If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued.
For more information see: Practical completion.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.