Rolling wave programming
Programmes describe the sequence in which tasks must be carried out so that a project (or part of a project) can be completed on time. They offer a view of how the project will be divided into activities, the duration of those activities, and logic links to preceding and succeeding activities.
Programmes may be depicted as Gantt charts, bar charts, line-of-balance diagrams, pure logic diagrams, time-scaled logic diagrams, time-chainage diagrams and so on.
For more information see: Programme for building design and construction.
Rolling wave programming (or rolling wave planning) is a method of programme development in which the details of the programme are progressively elaborated as the project proceeds. This is based on the assumption that it will be possible to develop the plan for specific activities in more detail closer to the time that they are actually executed.
Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
NB Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that planning packages (PPs): ‘…represent work that cannot yet be planned as work packages because of a lack of detailed information. They must be converted into work packages before they can commence.’
It proposes that: ‘The requirement for a periodic conversion, from planning package to work package, is the result of setting up the project using rolling wave planning, whereby only the current phase of a project is planned in detail and future phases are planned in outline. The conversion process is a fundamental aspect of project control using EVM (earned value management) and results in a more controlled project baseline.’
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.