Recording dayworks
Contents |
[edit] Introduction
Daywork is a means by which a contractor is paid for instructed work based on the cost of labour, materials and plant plus a markup for overheads and profit. It is generally used when work cannot be valued in the normal way. For example, daywork might be instructed when there are no comparative rates in a bill of quantities and a pro-rata method of pricing cannot be used. This method of pricing can be open to exploitation, so it is advisable to put monitoring and controlling procedures in place.
[edit] Recording dayworks
Contractors will usually have a template or daywork sheet to capture labour hours, materials and plant. Dayworks can either be, percentage addition or all-inclusive rates. With all-inclusive dayworks a pre-established schedule of rates submitted at tender is used to price the daywork.
A typical daywork sheet might contain the following:
- Project details.
- Instructions issued by the client or site instructions.
- Date (some contractors capture a week's work on a daywork sheet).
- Description of the dayworks.
- Details of labour, including workers' names and hours worked.
- Details of all materials used.
- Details of all plant used.
- Add on costs – profit and overhead.
- Signature area for the contractor’s representative.
- Signature area for the client’s representative.
The client’s team on-site should monitor the daywork. If a clerk of works is part of the client team, monitoring dayworks will typically be their duty. They will verify the hours captured and plant and materials used and sign off the daywork sheet. Their signature will only verify the data captured on-site and not that the daywork sheet is a valid claim for the final account.
[edit] Conclusion
Daywork instructions can be a contentious issue in the industry, and programme pressures can affect the clarity of works instructed. Clear communication between the contractor and the client’s team is vital to minimise disputes, including clear instructions relating to time scales and procedures that must be followed.
[edit] Related articles on Designing Buildings
- Abortive work in building design and construction.
- Architect's instruction.
- Change order for construction contracts.
- Construction contract.
- Change control procedure for building design and construction.
- Compensation event.
- Bill of quantities BOQ.
- Confirmation of verbal instruction.
- Dayworks in construction.
- Payment for extra work.
- Valuation.
- Valuation of interim payments.
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.