Dayworks in construction
Daywork is a means by which a contractor is paid for specifically instructed work on the basis of the cost of labour, materials and plant plus a mark up for overheads and profit. It is generally used when work cannot be priced in the normal way.
NRM2, RICS new rules of measurement, Detailed measurement for building work defines daywork as; '... the method of valuing work on the basis of time spent by the contractor’s workpeople, the materials used and the plant employed.'
Examples of when daywork may be applied are when unforeseen obstructions are encountered during ground works or when work is instructed for which there are no comparative rates in a bill of quantities.
It is usual for most contracts to contain clauses that provide a method of evaluating variations, additional work and instructions by using existing contract rates and prices. NEC contracts favour pre-agreed sums based on acceptance of a contractor’s quotation.
There are two basic options as to how daywork rates can be priced:
Option A – a percentage addition
- Prime cost to which a percentage is added for overheads, profit and incidental costs.
Option B – all inclusive rates
- All inclusive rates are quoted at tender and incorporated in the contract documents. These include an allowance for overheads and profit, either fixed for the period of the contract, or, in the case of contract conditions that are index linked, subject to an inflation allowance.
[edit] Related articles on Designing Buildings
Featured articles and news
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Comments
There is a great mobile phone App that lets you quickly create a daywork or just a resource estimate and send it to the office in minutes, the App date stamps start and finish photos to help you prove the record is a true reflection of the works. It also allows you to quickly get pre-authorisation of the daywork prior to starting the works. Here's the link http://www.constructionrates.co.uk/Rate_Gen/Android_Mobile_Tablet_Smart_Phone_Daywork_App_UK_Construction_Industry.htm