Priced bill of quantities
A bill of quantities is a document prepared by the client's cost consultant that provides measured quantities of the items of work necessary to construct a development. These items of work are described by the drawings and specifications in the tender documentation. The quantities may be measured in number, length, area, volume, weight or time.
An unpriced bill of quantities (sometimes referred to as the tender pricing document) is issued to tenderers, who will then estimate their price for each item. This priced bill of quantities constitutes the tenderer's complete offer. It is the unpriced bill of quantities, but with the tenderer’s rates, costs and totals added.
The preparation, by the client’s consultants, of an unpriced bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking-off quantities from the drawings and specifications themselves), it provides a fair and accurate system for tendering. It also makes it possible to compare both the overall price and individual items directly with other tenderers’ offers, allowing a detailed assessment of which aspects of a tender may offer good or poor value. This information can assist with tender negotiations.
The priced bill of quantities will also:
- Assist with the agreement of the contract sum with the successful tenderer.
- Provide a schedule of rates assisting with the valuation of variations.
- Provide a basis for the valuation of interim payments.
- Provide a basis for the preparation of the final account.
It is very important that bills of quantities are prepared according to a standard, widely recognised methodology. This helps avoid any ambiguities or misunderstandings and so helps avoid disputes arising through different interpretations of what has been priced. In the UK, bills of quantities for general construction works will most commonly be prepared in accordance with the Standard Method of Measurement 7th Edition (SMM7) or the New Rules of Measurement, which became operative on 1 January 2013 and replaced SMM7 on 1st July 2013.
Bills of quantities are most useful to the contractor when they are prepared in work sections that reflect likely sub-contract packages. This makes it easier for the contractor to obtain prices from sub-contractors and is more likely to result in an accurate and competitive price.
[edit] Related articles on Designing Buildings Wiki
- Bill of quantities.
- Common arrangement of work sections.
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- New Rules of Measurement.
- Schedule of rates.
- Schedule of work.
- Standard Method of Measurement.
- Tender documentation.
- Tender pricing document.
- Types of bill of quantities.
- Unpriced bill.
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).