Planning and managing Hinkley Point C
Contents |
[edit] Introduction
In early-2017, the Institution of Civil Engineers (ICE) hosted a networking evening with EDF Energy to discuss project planning for Hinkley Point C, the first nuclear power station in the UK in over a generation and the largest infrastructure project of the decade.
The evening featured presentations from David Speight, EDF Energy’s Head of Civil Construction, Nuclear New Build and Sarah Williamson, Laing O’Rourke Technical Director. The presentations were sought to answer some of the pressing questions the industry has regarding the project.
[edit] How can the project be delivered on cost and on time?
David Speight highlighted that previous experience of developing nuclear power plants in France meant that EDF was able to formulate a strong set of project values and culture based on lessons learned.
These values all stem from an overriding focus on quality and aim to ensure that humility, respect, solidarity, positivity and clarity permeate through the workforce. In order to facilitate this, each meeting starts with a safety message that focuses on previous examples of accidents onsite.
This approach has seen some success, as in December 2016, the Hinkley Point construction team (HPC) was able to confirm that they had one million man hours without lost time for injury.
[edit] How can HPC mitigate making construction errors onsite?
Sarah Williamson contextualised the enormity of the project by explaining that the joint venture between Bouygues and Laing O’Rourke (BYLOR) will have to produce 50 million bent bars, equivalent to the number of grass blades on three tennis courts.
She said that was why it was imperative there are no mistakes onsite as it cannot be built twice. To limit construction errors in the first instance, BYLOR decided designs need to be 3D, clash-free and buildable onsite.
In order to achieve this, they have been employing 3D modelling allowing designers to build each component of the plant virtually as many times as they need to, before creating a design they can guarantee will be successful onsite.
This approach will not only account for lowering onsite errors only but also increase efficiency rates and reduce the likelihood of health and safety issues.
[edit] What are the next steps in the project?
Both speakers stressed that in less than 50 days they will be laying the first concrete of the first nuclear new build of this generation, already a critical project milestone.
In 2017, they also have the following objectives to complete:
- Start of HPC site accommodation campus.
- First safety-related concrete used in gallery.
- Completion of east welfare building.
- Handover of civil works design studies for reactor pre-stressing gallery.
- Handover of civil works design studies for pumping station raft.
- Start installation of seawater cooling pipes.
EDF and Laing O’Rourke mentioned the importance of limiting errors. For further knowledge on health and safety see the Management of Contractors as part of ICE's health and safety series.
The EDF evening was part of ICE’s Energy, Resilience and Climate Change campaign.
This article was originally published here by ICE on 22 February 2017. It was written by Claire Miller.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Update on the future of Grenfell Tower
Deputy Prime Minister decides for it be carefully taken down to the ground.
Ending decades of frustration, misinformation and distrust.