Planning and managing Hinkley Point C
Contents |
[edit] Introduction
In early-2017, the Institution of Civil Engineers (ICE) hosted a networking evening with EDF Energy to discuss project planning for Hinkley Point C, the first nuclear power station in the UK in over a generation and the largest infrastructure project of the decade.
The evening featured presentations from David Speight, EDF Energy’s Head of Civil Construction, Nuclear New Build and Sarah Williamson, Laing O’Rourke Technical Director. The presentations were sought to answer some of the pressing questions the industry has regarding the project.
[edit] How can the project be delivered on cost and on time?
David Speight highlighted that previous experience of developing nuclear power plants in France meant that EDF was able to formulate a strong set of project values and culture based on lessons learned.
These values all stem from an overriding focus on quality and aim to ensure that humility, respect, solidarity, positivity and clarity permeate through the workforce. In order to facilitate this, each meeting starts with a safety message that focuses on previous examples of accidents onsite.
This approach has seen some success, as in December 2016, the Hinkley Point construction team (HPC) was able to confirm that they had one million man hours without lost time for injury.
[edit] How can HPC mitigate making construction errors onsite?
Sarah Williamson contextualised the enormity of the project by explaining that the joint venture between Bouygues and Laing O’Rourke (BYLOR) will have to produce 50 million bent bars, equivalent to the number of grass blades on three tennis courts.
She said that was why it was imperative there are no mistakes onsite as it cannot be built twice. To limit construction errors in the first instance, BYLOR decided designs need to be 3D, clash-free and buildable onsite.
In order to achieve this, they have been employing 3D modelling allowing designers to build each component of the plant virtually as many times as they need to, before creating a design they can guarantee will be successful onsite.
This approach will not only account for lowering onsite errors only but also increase efficiency rates and reduce the likelihood of health and safety issues.
[edit] What are the next steps in the project?
Both speakers stressed that in less than 50 days they will be laying the first concrete of the first nuclear new build of this generation, already a critical project milestone.
In 2017, they also have the following objectives to complete:
- Start of HPC site accommodation campus.
- First safety-related concrete used in gallery.
- Completion of east welfare building.
- Handover of civil works design studies for reactor pre-stressing gallery.
- Handover of civil works design studies for pumping station raft.
- Start installation of seawater cooling pipes.
EDF and Laing O’Rourke mentioned the importance of limiting errors. For further knowledge on health and safety see the Management of Contractors as part of ICE's health and safety series.
The EDF evening was part of ICE’s Energy, Resilience and Climate Change campaign.
This article was originally published here by ICE on 22 February 2017. It was written by Claire Miller.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.


























