Penultimate certificate for construction contracts
The JCT minor works building contract (MW 16) includes provision for a ‘penultimate certicate’, which signifies that there is no more work to value and triggers the final progress payment. Once issued, only the final certificate remains.
The due date for payment is 7 days after practical completion and the penultimate certificate must be issued within 5 days of the due date. The final date for payment is 14 days from the due date.
The difference between the penultimate certificate and a normal certificate for a progress payment is that half the retention is now released. Retention is a percentage of the amount certified as due to the contractor that is retained by the client to ensure that the contractor properly completes the works. So for example if the total retention was 5%, then 97.5% of the amount owed will become payable once the penultimate certificate has been issued, rather than 95% under a normal progress payment.
There will be no further payments until any defects that become apparent have been rectified and the final certificate is issued. At this point the final payment will be made, including the release of the remaining retention.
The Housing Grants Construction and Regeneration Act (The Construction Act) sets out requirements for making payments under construction contracts, including a requirement to issue a pay less notice (previously a withholding notice) if the client intends to pay less than the amount set out in a payment notice, setting out the basis for its calculation. See The Construction Act for more information.
NB There is no provision for the penultimate certificate to be withheld once practical completion has been certified. This means that certifying practical completion is a crucial point in the progress of the works, when the penultimate payment is triggered, the contractor’s liability for liquidated damages ceases and the client takes possession of the site. See practical completion for more information.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.
The due date for interim payment following practical completion is 7 days under MW11 not 14 days with certification required within 5 days then payment within 14 days.