Penultimate certificate for construction contracts
The JCT minor works building contract (MW 16) includes provision for a ‘penultimate certicate’, which signifies that there is no more work to value and triggers the final progress payment. Once issued, only the final certificate remains.
The due date for payment is 7 days after practical completion and the penultimate certificate must be issued within 5 days of the due date. The final date for payment is 14 days from the due date.
The difference between the penultimate certificate and a normal certificate for a progress payment is that half the retention is now released. Retention is a percentage of the amount certified as due to the contractor that is retained by the client to ensure that the contractor properly completes the works. So for example if the total retention was 5%, then 97.5% of the amount owed will become payable once the penultimate certificate has been issued, rather than 95% under a normal progress payment.
There will be no further payments until any defects that become apparent have been rectified and the final certificate is issued. At this point the final payment will be made, including the release of the remaining retention.
The Housing Grants Construction and Regeneration Act (The Construction Act) sets out requirements for making payments under construction contracts, including a requirement to issue a pay less notice (previously a withholding notice) if the client intends to pay less than the amount set out in a payment notice, setting out the basis for its calculation. See The Construction Act for more information.
NB There is no provision for the penultimate certificate to be withheld once practical completion has been certified. This means that certifying practical completion is a crucial point in the progress of the works, when the penultimate payment is triggered, the contractor’s liability for liquidated damages ceases and the client takes possession of the site. See practical completion for more information.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.
The due date for interim payment following practical completion is 7 days under MW11 not 14 days with certification required within 5 days then payment within 14 days.