Operational rate estimating
Contents |
[edit] Introduction
Operational rate estimating is a method used to calculate building costs. In operational rate estimating a distinct parcel of work is priced as a package. This is as opposed to projects where each unit of the bill of quantities are priced individually.
The estimator will still need to calculate all the individual items that are required in unit rate estimating , such as labour, plant and materials, but the key difference in operational estimates is that the estimator views a section of the work as a whole rather than as a set of separate items.
[edit] Operational Rate
Operational rate estimating is commonly used in the civil engineering industry. This is generally due to the larger quantities involved in civil engineering projects. The plant and machinery required in civil engineering works can also play a more significant role in the project. Operational estimating is preferred in plant-dominated projects.
Operational rate estimating can also be be used for pricing in design and build contracts where the contractor is responsible for their own pricing methods and a bill does not have to be produced.
The estimator will calculate all the resources needed for parts of the construction packages together rather than in isolation. Operational estimating will involve forecasting the cost of completing a construction operation, which may consist of many bill items.
Operational estimating will require a completed:
It is usually beneficial for the estimator to work alongside the operational teams to prepare the resource schedules and programmes as they may require comparative estimates or cost alternatives to help adopt the most suitable approach and achieve value for money.
Typical packages in operational estimating are:
[edit] Related articles on Designing Buildings Wiki
- All-in rates.
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Capital.
- Contract sum.
- Cost control.
- Cost engineering.
- Cost information.
- Cost plan.
- Elemental cost plan.
- Estimating
- Initial cost appraisal.
- Measurement.
- New Rules of Measurement.
- Order of cost estimate.
- Pre-tender estimate.
- Tender cost.
- Unit rate estimating.
[edit] External references
- Quantity Surveyor’s Pocket Book by Duncan Cartlidge.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Why being a mentor can help your career.
Channel 4 broadcaster to host 125th anniversary ceremony.
Listed structures on the rail network
Heritage interests and operational requirements must be balanced.
Historic England publishes research into embodied carbon when retrofitting traditional buildings.
New Prime Minister delivers on ECA call for cut in electricity costs.
CIOB reacts to the announcement of Andy Burnham as Prime Minister.
Heritage and conservation science workforce survey - Have your say.
England's Suburbs 1820-2020. Book review.
New, more proportionate and targeted approach for higher-risk building assessments.
Government brings British Steel into public ownership.
UKCW Birmingham returns with bold new theme and focus.
New guidance published on competence requirements for self-certification schemes.