Operational rate estimating
Contents |
[edit] Introduction
Operational rate estimating is a method used to calculate building costs. In operational rate estimating a distinct parcel of work is priced as a package. This is as opposed to projects where each unit of the bill of quantities are priced individually.
The estimator will still need to calculate all the individual items that are required in unit rate estimating , such as labour, plant and materials, but the key difference in operational estimates is that the estimator views a section of the work as a whole rather than as a set of separate items.
[edit] Operational Rate
Operational rate estimating is commonly used in the civil engineering industry. This is generally due to the larger quantities involved in civil engineering projects. The plant and machinery required in civil engineering works can also play a more significant role in the project. Operational estimating is preferred in plant-dominated projects.
Operational rate estimating can also be be used for pricing in design and build contracts where the contractor is responsible for their own pricing methods and a bill does not have to be produced.
The estimator will calculate all the resources needed for parts of the construction packages together rather than in isolation. Operational estimating will involve forecasting the cost of completing a construction operation, which may consist of many bill items.
Operational estimating will require a completed:
It is usually beneficial for the estimator to work alongside the operational teams to prepare the resource schedules and programmes as they may require comparative estimates or cost alternatives to help adopt the most suitable approach and achieve value for money.
Typical packages in operational estimating are:
[edit] Related articles on Designing Buildings Wiki
- All-in rates.
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Capital.
- Contract sum.
- Cost control.
- Cost engineering.
- Cost information.
- Cost plan.
- Elemental cost plan.
- Estimating
- Initial cost appraisal.
- Measurement.
- New Rules of Measurement.
- Order of cost estimate.
- Pre-tender estimate.
- Tender cost.
- Unit rate estimating.
[edit] External references
- Quantity Surveyor’s Pocket Book by Duncan Cartlidge.
Featured articles and news
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.