Non-compliant tender
This article describes in detail the tender process for a typical commercial construction contract.
For a wider description of the range of tender processes that might be adopted on different types of project, see Tender processes.
For more information about different contractual procurement routes, see Procurement route.
An invitation to tender will generally include very specific requirements for the information and format of the tender that prospective suppliers must submit. This ensures that necessary information is included and that it is in a format that the client is able to analyse and compare with other tenders.
If a prospective contractor or supplier submits a tender that does not comply with the client's requirements then that bidder is said to have submitted a non-compliant bid. This can result in the tender being rejected. Full compliance requires that all material conditions of the invitation to tender must be complied with.
A tender may be non-compliant by:
- Not answering all the question(s).
- Exceeding the required word length.
- Submitting in the wrong format e.g PDF when Excel or Word were required.
- Making a late submission.
- Not breaking down information in the correct way.
- Submitting proposals that do not comply with the client's requirements.
However, a non-compliant proposal, sometimes referred to as a variant bid, may be submitted intentionally if the tenderer believes that an alternative could offer better value for money that the requirements set out in the invitation to tender. However, non-compliant proposals should only be submitted if they have been requested or are explicitly permitted by the client, and they may need to be accompanied by a compliant bid to allow direct comparison with other tenders.
See also: Qualified bid.
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Bid writer.
- Competitive tender.
- Contract award.
- Contract conditions.
- Contract documents.
- Due diligence when selecting contractors or subcontractors.
- Invitation to tender.
- Letter of award.
- Mid-tender interview.
- Most Economically Advantageous Tender (MEAT).
- Pre-tender interview.
- Procurement route.
- Qualified bid.
- Selection criteria.
- Tender documentation.
- Tender evaluation.
- Tender processes.
Featured articles and news
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.