Meaning of quantum meruit
Quantum meruit is a Latin term meaning ‘the amount deserved’ or ‘what the job is worth’. It is used to refer to a claim for a reasonable sum, such as when a contractor seeks payment for work which has not been determined by a contract. If there is a contract that entitles one party to receive an agreed or reasonable sum from the other then the law of contract applies and a claim for quantum meruit cannot be used.
A claim may arise in circumstances, including:
- Where there is a quasi-contract (e.g. where some contractual terms have been agreed but price has not).
- Where no price has been fixed.
- Where there is work done that falls outside the contract.
- Where there is work done under a void or unenforceable contract.
The contractor must demonstrate that the employer requested, either expressly or impliedly, the work to be done, or freely accepted it. However, in practice, it can prove difficult for the contractor to prove the exact amount of their entitlement under the principle of quantum meruit.
There are no stipulations as to how the reasonable sum is to be assessed as circumstances often differ. The assessment of a claim for quantum meruit in the absence of a contract will differ from the assessment of a reasonable sum to be paid within a contractual framework. Where work done outside an existing contract gives rise to a quantum meruit claim, the contractor should be paid at a fair commercial rate rather than as though it had been performed under the contract (which may be a different rate).
Evidence that can prove useful to a claim includes:
- Any abortive negotiations relating to price.
- The prices in a related contract.
- Calculations based on the net cost of labour and materials.
- Expert opinions regarding what constitutes a reasonable sum.
[edit] Related articles on Designing Buildings Wiki
- Construction contract.
- Contract conditions.
- Contract law.
- Contract sum.
- Defined cost.
- Difference between lump sum and measurement contracts.
- Disallowed cost.
- Glossary of property law terms.
- Letter of intent.
- Loss and expense.
- Payment for extra work.
- Remeasurement.
- Retention.
- Right to payment.
- The distinction between liquidated damages clauses and penalty clauses.
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).