Managing the risks of state events following the Queen’s death
[edit] Current position?
With the passing of HM Queen Elizabeth II, a large majority of individuals and businesses are having to grapple with the unprecedented event of the death of a monarch.
The UK is currently in a period of mourning and with 19 September 2022, the day of the state funeral, having been declared a national bank holiday, questions have arisen as to the potential cascading effects that may permeate through the construction industry during this period.
The Department for Business, Energy & Industrial Strategy has given notice of the upcoming bank holiday and has stated there will be no statutory entitlement to time off, leaving it as a discretionary matter ‘for discussion between individuals and their employer’.
[edit] What are the contractual implications?
ECA Members are encouraged to talk to employers and clients and to check their contracts to ascertain whether they will have a right to time and money due to any potential disruption or delay caused by the state funeral and other ancillary arrangements which may disrupt project delivery.
The obvious implications of a declared bank holiday are that it may give rise to a worker expectation that where the day is worked, workers should receive additional remuneration to compensate for the loss of a bank holiday. Members will need to factor this into the management of their business and project management administration and cost considerations.
As parties may have entered into bespoke contractual arrangements an entitlement to time and money will be dependant upon the provisions of each individual contract. However, there are some general points our Members should take into consideration.
If an employer/main contractor expressly instructs work to stop on site on the day of the bank holiday, for example in order to allow employees to attend the state funeral or to not have loud machinery in use on site out of respect during the bank holiday, then Members will have a strong case to argue that such an instruction constitutes a variation/change under the contract and therefore a Member (who is a sub-contractor) should be able to claim for time and loss & expense/compensation. These are covered under relevant events under the JCT suite of contracts (clauses 2.23 to 2.26 of the JCT D&B and clauses 2.26 to 2.29 of the JCT SBC) and under compensation events for the NEC 3 and NEC 4 ECC (section 6).
On the other hand, if an employer/main contractor does not issue any specific instructions for work to cease on site and, for example, leaves the option to pay respects to the discretion of the supply chain, then Members which the supply chain must be prepared to play catch up, as it will be more difficult to prove an entitlement to time and money if Members choose to forego a day’s productivity as this is unlikely to amount to a relevant event or a compensation event.
In such an instance, we would advise Members to weigh up the commercial risks of falling slightly behind on a project and having to catch up, against the decision to allow their workforce the opportunity to pay their respects on a day of national mourning.
Regardless, Members should factor-in the requirements to issue appropriate notices (via the notice requirements) for; extension of time, loss & expense, early warning and compensation vent as may be required by the contract. If you don’t operate the machinery, you can’t claim an entitlement.
We would encourage our Members to maintain an open line of communication with employers/main contractors during these times as this is an unprecedented event and there is an industry wide push for collaboration between parties.
If we have learnt anything from Covid-19, it is that clear dialogue and record keeping regarding arrangements, expectations, float, programme and cost implications will give parties the best opportunity to appropriately allocate risk and ensure that any contractual mechanisms in place are followed. This should minimise delay and disruption and ensure Members are compensated.
Members may also want to consider that where ‘dayworks’ are a contractually valid method of valuing variations or changes, these will be inherently linked to the unionised wage rates calculated on the basis of 8 public holidays in an ordinary year. This year we have had 9 bank holidays due to the Platinum Jubilee, and if the state funeral is declared by the relevant sector agreement to be an additional bank holiday it will introduce a 10th bank holiday, leading to a potential further loss of productivity and increasing the resulting costs of employers.
The proximity of the 19th of September, under a best-guess scenario is likely to see an additional days’ leave granted at normal wage rates to be used either on the 19th or before the end of 2022 at the employer’s discretion.
Member companies who are part of the JIB are advised to check the JIB website in the week leading up to the state funeral to seek confirmation of the agreed position. Non JIB Members will have discretion to enter into daywork rates negotiation and will have the option to adopt the JIB model should they wish to do so.
This article originally appeared under the same title on the ECA news and blog site, it was written by Obaid Bin-Nasir, Legal and Commercial Advisor ECA dated September 14, 2022.
--ECA
[edit] Related articles on Designing Buildings
Featured articles and news
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.
Setting Expectations on Competence Management
Industry Competence Committee.
New Scottish and Welsh governments
CIOB stresses importance of construction after new parliament elections.
The sad story of Derby Hippodrome
An historic building left to decay.
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.





















