Level access shower
The building regulations set out legal requirements for specific aspects of building design and construction. A series of approved documents provide general guidance about how different aspects of building design and construction can comply with the building regulations.
Approved document M provides guidance for satisfying Part M of the building regulations: Access to and use of buildings, which requires the inclusive provision of ease of access to, and circulation within, buildings, together with requirements for facilities for people with disabilities.
Approved document M, Volume 1: Dwellings (2015 edition incorporating 2016 amendments) defines an installed level access shower as a:
Step-free area with no lips or upstands, suitable for showering, with a floor laid to shallow falls towards a floor gulley connected to the drainage system. |
Depending on the type of dwelling and number of bedspaces, the approved document may require an installed level access shower to be provided, and rooms that contain installed level access showers may be required to be constructed as a wet room, and may need to have the potential for a bath to be installed above it.
Where a wet room is a:
WC or bathroom compartment with tanking and drainage laid to a fall to a connected gulley capable of draining the floor area when used as a shower. |
A potential level access shower is a:
Space capable of providing a level access shower without the need to move walls, remove screed or other solid flooring. It should include a capped-off floor gulley, set at an appropriate level and connected to the drainage system. (Usually provided within a wet room). |
[edit] Related articles on Designing Buildings
Featured articles and news
ECA Industry Awards 2024 shortlist revealed
22 leading businesses from across the electrotechnical and engineering services sector.
Government unveils Skills England strategy
Skills England to transform opportunities and drive growth.
New Government Hub for York Given Planning Green Light
For up to 2,600 civil servants, due for completion by 2028.
Construction Skills Certification Scheme cards
July update on Professionally Qualified and Academically Qualified Person Cards.
BSRIA Briefing 2024, November 22
Sustainable Futures: Redefining Retrofit for Net Zero Living.
The CLC on driving competency in the retrofit sector
Previously published roadmap on skills for net zero.
The first labour government King's speech in fifteen years
Construction industry reactions, support and some concern.
CIOB Retrofit of Buildings Technical Information Sheet
What retrofit is, the approach to be taken and processes to be followed.
Adapting Historic Buildings for Energy and Carbon Efficiency
Historic England advice note 18, free download published.
10 retrofit projects revisited 10 years after completion.
Information orders, building liability orders and SPVs
Key BSA terms and how they impact special purpose vehicles.
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.