How to serve a party wall Notice
Contents |
[edit] The Complete Guide to Serving Party Wall Notices
If you're planning construction or renovation work on your property and share a boundary or wall with your neighbour, you are legally required to comply with the Party Wall etc. Act 1996. The first step in this process is serving a Party Wall Notice. This guide will explain the exact process of serving a Party Wall Notice, ensuring you meet your legal obligations and maintain good relations with neighbouring property owners.
[edit] Step 1: Understand the Party Wall Notice Requirements
A Party Wall Notice is a formal document that informs adjoining property owners about proposed construction work that could affect a shared boundary or structure. The types of work that require a Party Wall Notice include:
- Building on or at the boundary of two properties.
- Excavating within 3 to 6 meters of a neighbouring building.
- Making structural changes to a shared (party) wall.
Before you serve the notice, it is essential to determine the type of work you’re planning and its potential impact on neighbouring properties.
For professional advice tailored to your situation, consider consulting Icon Surveyors, experienced in all aspects of Party Wall Surveying and serving Party Wall Notices.
[edit] Step 2: Types of Party Wall Notices
There are three types of Party Wall Notices:
- Line of Junction Notice: If you plan to build a new wall on the boundary.
- Party Structure Notice: If the work affects an existing party wall, such as altering it or repairing it.
- Notice of Adjacent Excavation: If you plan to dig near the foundation of a neighbouring building.
- Each type of notice must include specific details about the proposed work, including:
- The full names and addresses of all property owners involved.
- A detailed description of the planned work.
- The proposed start date of the work.
To ensure your notice is compliant and correctly served, it's advisable to have a qualified surveyor assist with this process. Learn more about the specifics from Icon Surveyors, specialists in handling Party Wall matters.
[edit] Step 3: Serving the Notice
The next step is serving the Party Wall Notice. You can do this in one of the following ways:
- Hand Delivery: Deliver the notice personally to the adjoining owner.
- Mail: Send the notice via recorded delivery to ensure there is proof of receipt.
- Post on the Property: If the adjoining owner’s address is unknown, the notice can be posted on a conspicuous part of the property.
Once the notice has been served, the adjoining owner has 14 days to respond. The response options are:
- Consent: The neighbour agrees to the work proceeding as outlined in the notice.
- Dissent and Appoint a Surveyor: The neighbour dissents and appoints their own Party Wall Surveyor. Alternatively, both parties can agree to use a single surveyor, known as the Agreed Surveyor.
- No Response: If there is no response within 14 days, it is considered a dissent, and a surveyor must be appointed to create a Party Wall Award.
For assistance in serving the notice correctly and navigating any potential disputes, you can rely on Icon Surveyors, who offer specialised services to manage the Party Wall process from start to finish.
[edit] Step 4: Appointing Surveyors and Drafting the Party Wall Award
If the adjoining owner dissents or does not respond, surveyors must be appointed. The appointed surveyor(s) will prepare a Party Wall Award, which is a legally binding document detailing:
- The work to be done.
- The schedule of work.
- Rights and responsibilities of each party.
- Protective measures to minimise damage or disruption.
The Party Wall Award also includes a Schedule of Condition report, which records the state of the adjoining property before work begins. This ensures that any claims for damage caused by the work can be verified.
[edit] Step 5: Final Steps and Compliance
Once the Party Wall Award is agreed upon and signed, work can commence. It’s important to adhere strictly to the details outlined in the Award to avoid disputes or potential legal action. During the work, your surveyor may perform periodic inspections to ensure compliance with the terms of the Party Wall Award.
[edit] Conclusion
Serving a Party Wall Notice can be a complex process, but understanding each step and seeking professional guidance can make it straightforward and manageable. By ensuring that you serve the correct notice in the proper manner, you minimise the risk of disputes and ensure a smoother construction process. For expert assistance with serving Party Wall Notices and managing Party Wall Agreements look at the header above.
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).