Line of junction notice
A line of junction, is an imaginary line that separates the land of adjoining owners.
Section 1 of the Party Wall etc. Act applies where lands of different owners adjoin and:
- are not built on at the line of junction; or
- are built on at the line of junction only to the extent of a boundary wall (not being a party fence wall or the external wall of a building),
and either owner wishes to build on any part of the line of junction.
The notice must be served by the party wishing to build the wall, at least one month before they intend the building work to start, giving a description of the proposed works.
Having been served with the notice, the adjoining owner must serve a notice indicating their consent. This stipulates that the wall should be built on half of the land of each owner or in another position that they may agree on, and that the expense of the wall shall be split between them depending on the use that has been, or is to be, made by them.
If the adjoining owner does not consent, then the building owner is only able to build the wall at their own expense and it must be entirely on their land. They may still, within 12 months, place below the level of the land of the adjoining owner projecting footings and foundations necessary for the construction of the wall. They must compensate any adjoining owner and any adjoining occupier for any damage to their property.
A template line of junction notice is as follows:
|
To: (Adjoining Owner) of: [Address] I/We (Building Owner) of: [Address] as owner(s) of the land and premises known as: [name and number] which adjoins your premises known as: [name and number] I/we hereby serve NOTICE on you Under Section 1 (2), subject to your written consent it is intended to build on the line of junction of the said lands a *party wall/party fence wall. Under Section 1 (5) it is intended to build on the line of junction of the said lands a wall wholly on *my/our own land. Under Section 1 (6) it is intended to place projecting footings and foundation on your land at *my/our expense. The accompanying drawings show the proposed works which are: [details of the works] I/we propose to commence the works after the expiration of one month from the date of this notice or earlier if you agree. In the event of a dispute arising for settlement *I/we would appoint as *my/our surveyor: [name and details of surveyor] Signed Date |
[edit] Related articles on Designing Buildings
Featured articles and news
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.