Henry Boot Construction Ltd v Alstom Combined Cycles
The case of ‘Henry Boot Construction Ltd. v Alstom Combined Cycles’ [1999] set a precedent that contractor’s rates do not become reasonable or unreasonable by the execution of variations.
The extent to which bill of quantities (BoQ) rates are applicable for valuing variations in the works, is a common cause of conflict on projects, particularly when there are substantial changes in quantities. This can be a particular issue if the rate in question is abnormally high or low due to the fact that an error has been incurred. Contractors argue that abnormally low rates compound losses, while clients point out that abnormally high rates exaggerate contractor profits.
In the case of Henry Boot Construction Ltd. v Alstom Combined Cycles, Henry Boot Construction Ltd. was employed by Alstom to undertake civil engineering works at a power station. Boot quoted a price for temporary sheet piling and this figure was included in the contract. As the works proceeded however, variation instructions affecting the sheet piling were issued.
Boot’s price was found to have been calculated incorrectly, meaning that the additional quantity required by the variation would have given them a large profit. Boot argued that the contract rates must be adhered to whereas Alstom argued that a fair valuation should be made.
At the trial, the judge emphasised the importance of the contract rates, ruling that they were ‘sacrosanct, immutable, and not subject to correction’ on the basis of one party’s dissatisfaction with them. He referred to Clause 55(2) in the relevant ICE Standard Form (6th ed.) contract which stipulated that there should be no rectification of errors, omissions or estimates, and that a mistake in a rate or price bound both parties equally.
The Court of Appeal endorsed the judge’s ruling in 2000, confirming that pricing errors do not allow the parties to adjust the rates.
The rates may however be adjusted where they are used to value variations:
- Where the works are not executed under similar conditions.
- Where the rate is rendered inapplicable by a substantial change in the quantities.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.