FC Twente stadium roof collapse
This article addresses how the industry can learn from the fatal consequences of the collapse at the FC Twente Stadium in Holland in 2011.
The main aspects which flow out of the report are:
- The main contractor must coordinate the activity of all subcontractors.
- There must be coordination of the design process and integration of the various interfaces to ensure there is good fit within the respective tolerances of the connecting components.
- Temporary conditions are often more onerous than permanent ones. Temporary works must be designed to accommodate temporary loads and any change to those loads should be advised to the temporary works designer to ensure those changes do not impact on his design.
- Sufficient time must be allocated to work activities.
- All activities should follow a defined method statement and sequence of work activities when critical to temporary stability. Any changes to that method statement and/or sequence should be referred to the originator/designer prior to any deviation.
- Operations should be signed off prior to follow-on trades starting.
What went wrong? Simply, the planned sequence of operations necessary to build such a structure was not followed. It would appear that there were a number of reasons.
- The erector’s programme of works was severely condensed.
- Concurrent activities took place which should have been sequential to ensure stability at all times.
- Respective tolerances were not allowed for in the design.
- Overly tight programme period allowed no float to rectify the lack of fit.
- Members were installed in a manner that induced stresses above working stresses.
- Members critical for temporary and permanent stability were not installed in sequence.
- The structure was loaded in its temporary condition prior to completion of necessary stability members. Materials were loaded on the structure in a way that produced a temporary condition more onerous than the permanent condition.
It appears that overly-tight completion dates were allowed to drive the programme in an unsafe manner. The programme, whilst important, must never over-rule safety. The CDM regulations in the UK place a number of responsibilities onto the client, not least the need to ensure sufficient resources and time are allocated to all steps in the design and construction sequence.
It may seem obvious but a structure made up from a number of components needs to be erected in a logical sequence to ensure there is stability at all times. That is an overriding factor. Stability issues can change as other members get added but there must be a clear understanding of loads, their load paths and stability throughout. Until a portion of structural works is handed over there should be no additional load, apart from its self-weight, applied to it unless agreed in writing with the author of the erection method statement. Loading-out of follow-on trades’ material is often a critical load case so one must carefully plan the timing of that load application and its position within the structure. Not only can incorrectly placed material cause local failure, it can also cause structure instability and collapse: in particular, the absence of sufficient counterbalance material will cause a cantilever to overturn.
The appointment of a competent Temporary Works Coordinator and the proper implementation of BS5975:2008 + A1:2011, Code of practice for temporary works procedures and the permissible stress design of falsework, should help lead to an avoidance of such events. One weapon in the temporary works designer’s armoury should be the precedence diagram. This defines activities (and part activities) which cannot start until another is complete. This is more than a mere statement of the construction sequence. It specifies the unique, essential, basis for the temporary works stages and should be put on a drawing and issued to the contractor.
In conclusion:
- Appoint a Temporary Works Coordinator and assign responsibilities.
- Leave responsibility and control of risks and hazards with those who are competent and best placed to control them.
- Do not blur those lines.
- If B must follow A, then ensure that happens and do not deviate unless advised by the originator that it is safe to do so.
- Do not work to impossible programmes, no matter what the client wants.
- Better to be alive and a few days late.
- One would hope that following the UK CDM regulations would prevent such an occurrence .
- However, hope should not be part of a safety regime.
This topic paper was published by SCOSS in July 2014. You can see the original paper here.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.