Enabling works for construction
Enabling works is a generic description for site preparation works that might take place prior to work under the main construction contract.
This could include:
- Demolition.
- Site clearance.
- Tree protection.
- Diversion and/or disconnection of existing site services.
- Geotechnical and exploratory ground investigation.
- Decoupling from existing buildings.
- Decontamination.
- Ground improvement and/or compaction.
- Excavation of known below-ground obstructions.
- Survey work.
- Creation of access routes.
- Perimeter fencing and security provisions.
- Work to neighbouring buildings.
- Discharging planning conditions that must be satisfied prior to construction commencing.
- Historical architectural investigation fieldwork.
- Access ramps.
- Signage provisions.
- Provision of statutory utilities to the site.
Enabling works might be preceded by 'mobilisation' activities, carried out after the client has selected the contractor, but before works commence on site. These are preparatory activities, such as; preparing method statements, arranging road closures, placing necessary sub-contracts, and so on. See Mobilisation for more information.
NB: NRM1: Order of cost estimating and cost planning for capital building work, defines enabling works as:
'...works executed ahead of the main building contract. Enabling works are employer and/or project team specified works, which might include a mixture of facilitating works and new building works (e.g. site preparatory works such as major demolition, removal of contaminated materials, reptile mitigation measures, and soil stabilisation; together with new sewers, new access road, new drainage, new retaining walls, and minor new building works).'
This is as opposed to facilitating works, which NRM1 defines as:
‘…all components measured and incorporated in group element 0 (i.e. Facilitating works). Includes specialist works which, normally, need to be completed before any building works can commence (e.g. major demolition works, soil stabilisation works and or temporary diversion of mains drainage).’
Advantages of having an enabling works contract:
- On site sooner.
- Can saves time and money.
- Could have a specialist contractor for carrying out that particular type of works eg. demolition.
Disadvantages:
- The cost and time to make up two separate contracts
- Process complexity involved in making up two separate contracts
- If there are two different contractors; liability and hand-over issues.
[edit] Related articles on Designing Buildings
Featured articles and news
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.