Cross-wall construction is a form of construction in which load bearing walls provide the primary vertical support and lateral stability for precast floors. External wall panels, lift cores or staircases are used to provide the required longitudinal stability. Bridging components such as floors, roofs and beams are supported by the load bearing walls or façade wall.
If both walls and floors are of cast in situ reinforced concrete, the series of ‘boxes’ so formed is sometimes referred to as ‘box frame construction’.
The system is ideal for buildings with cellular and orthogonal grids, with rooms of up to 4 x 9 m. It is suitable for buildings up to a height of five storeys where the floors are similar and where internal separating or party walls are required, such as in blocks of flats and student accommodation.
It creates a structurally efficient building with high levels of acoustic and fire separation between adjacent rooms. This is due to the high mass of the structure and good airtightness. Cross wall construction also has good thermal mass.
Cross-wall systems can offer significant time and cost savings in comparison to traditional building techniques as the components can often be prefabricated. In addition, the arrangement of windows between crosswalls is unrestricted.
The precast elements are typically brought to site 'just in time'. Hidden joints and ties, both horizontally and vertically are grouted in place as the work develops. Other works such as installation of mechanical and electrical services and finishes that are required can start prior to the completion of the entire structure.
Cross-wall construction involves a number of key connections:
- Wall-to-wall at vertical joints.
- Wall-to-wall at horizontal joints.
- Wall-to-base/foundation.
Care must be taken in both design and construction to ensure that the junctions between the non-load bearing claddings and the crosswalls are weather resistant.
If a pitched roof is to be included with the ridge parallel to the lateral axis, there will need to be an edge beam to provide a seating for the rafters and to transmit roof loads to the crosswalls.
[edit] Related articles on Designing Buildings Wiki
- Cavity wall.
- Cladding.
- Concrete frame.
- Diaphragm wall.
- Modular buildings.
- Offsite manufacturing.
- Off-site prefabrication of buildings: A guide to connection choices.
- Party wall.
- Precast flat panel system.
- Prefabricated structural panels.
- Prefabrication.
- Preventing wall collapse.
- Wall types.
[edit] External resources
- ‘Building Construction Handbook’ (6th ed.), CHUDLEY, R., GREENO, R., Butterworth-Heinemann (2006)
Featured articles and news
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
The Remarkable Pinwill Sisters: from ‘lady woodcarvers’ to professionals. Book review.
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Comments
Hi my house is of this design, I want to remove a timber and plasterboard partitionwall in my kitchen and make it bigger but am worried if it’s load bearing as it is pretty much the only interior wall downstairs of the house? Any help appreciated thanks in advance.
nick
If you're not certain, you should get a structural engineer to check it out for you. It should be relatively quick and straight forward job for them.