Competitive tender
Competitive tendering is a common method of procurement in the construction industry.
A tender is a submission made by a prospective supplier/contractor in response to an invitation to tender. It makes an offer for the supply of goods or services.
Those tendering for a contract are often competing with others, and generally, none of the tenderers are aware of the quotes provided by each other; therefore, they are incentivised to submit their most competitive tender. In this way, it is believed that competition in procurement can add value for the client.
Competitive tendering became increasingly common in the UK in the 1980s, when it was seen as a way of making public organisations open themselves up to bids from a number of different firms. This was intended to increase transparency, drive down costs, and improve the efficiency of state-funded organisations such as central and local government departments.
However, it has been criticised for placing too much emphasis on cost, and not necessarily achieving best value for the client. Competitive tendering can be seen as a 'race to the bottom' and can lead to disputes later in the project as suppliers seek mechanisms to increase their price.
Methods of assessing tenders which consider criteria other than the lowest cost include:
- Best value.
- Auction theory.
- Most Economically Advantageous Tender (MEAT).
- Mean value.
- Exclusion of the extremes.
- Weighted selection criteria.
- Balanced scorecard.
For more information see: Tender evaluation, and Procurement route.
NB The UN Procurement Practitioner's Handbook, produced by the Interagency Procurement Working Group (IAPWG) in 2006 and updated in 2012, defines competitive bidding as: 'A procurement method in which offers from competing suppliers are invited by open advertisement and provided with the scope, specifications, and terms and conditions of the proposed contract as well as the criteria by which the offers will be evaluated. The objectives of competitive bidding are to obtain goods or services at the lowest cost or best value through open and fair competition.'
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Best value procurement.
- Bid evaluation.
- Bid strategies.
- Compliant bid.
- Form of tender.
- Insourcing.
- Most economically advantageous tender (MEAT).
- Non-compliant tender.
- Preferred tenderer.
- Proposals.
- Single-stage tender.
- Tender.
- Tender evaluation.
- Two-stage tender.
- Variant bid.
- Why the lowest price isn't sustainable.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.