Clear width
The building regulations set out legal requirements for specific aspects of building design and construction. A series of approved documents provide general guidance about how different aspects of building design and construction can comply with the building regulations.
Approved document M provides guidance for satisfying Part M of the building regulations: Access to and use of buildings, which requires the inclusive provision of ease of access to, and circulation within, buildings, together with requirements for facilities for people with disabilities.
Approved document M, Volume 1: Dwellings (2015 edition incorporating 2016 amendments) defines a clear width as a:
| Clear distance measured between walls or other fixed obstructions (except permitted localised obstructions) or across a path. Skirtings totalling up to 50mm total thickness and shallow projecting ducts or casings above 1800mm may be discounted when measuring clear width. |
Where a localised obstructions is a:
| Short, fixed element such as a bollard lighting column or radiator, not more than 150mm deep that may intrude into a path, route, or corridor, that does not unduly restrict the passage of a wheelchair user. |
Depending on the type of dwelling, clear widths may be defined for; ramps and steps, approach routes, circulation areas, wheelchair storage and transfer spaces and private outdoor spaces.
Approved document M, Volume 2 sets out requirements for clear widths for wheelchair platform lifts in relation to buildings other than dwellings.
Both Volume 1 and Volume 2 also set out detailed requirements for door clear opening widths. See Door clear opening width for more information.
[edit] Find out more
Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Confronting competency, codes, capacity and costs.
The hidden risk in modern construction supply chains.
Construction Management, 10 June
24 months to 14: CITB launches accelerated apprenticeships.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.