CDM 2007 principal contractor
For information about the role of the principal contractor under the 2015 CDM regulations see CDM 2015 principal contractor.
The text below relates to the superseded 2007 CDM regulations and is provided as a historical reference.
The Construction (Design and Management) Regulations (CDM Regulations) are intended to ensure health and safety issues are properly considered during a project’s development so the risk of harm to those who have to build, use and maintain structures is reduced.
They were introduced in 1994 and came into force on 31 March 1995. They were substantially revised in 2007.
The regulations impose duties on:
- The client. (See CDM client for more information)
- Designers. (See CDM designers for more information)
- The CDM co-ordinator.
- The principal contractor.
- Contractors. (See CDM contractors for more information)
- Workers. (See CDM workers for more information)
The regulations require that a principal contractor is appointed for all notifiable projects as soon as practicable and at the latest before construction works begin. Notifiable projects are those which last more than 30 days or involve 500 person days of construction work.
The CDM co-ordinator must inform the Health and Safety Executive of the appointment of the principal contractor.
The main contractor will usually be the principal contractor. The principal contractor's role is to plan, manage and co-ordinate health and safety during construction.
The duties of the principal contractor include:
- Preparing a construction phase plan (at least an initial construction phase plan for the early stages of the works must be prepared before construction work can begin).
- Providing contractors with information allowing them to work safely.
- Ensuring co-operation and co-ordination between parties involved in the works.
- Ensuring that other contractors identify, assess and manage risks.
- Ensuring that welfare facilities are in place.
- Ensuring that the workforce is inducted, informed, trained and consulted.
- Taking steps to prevent unauthorised access to the site.
- Displaying the required F10 notice on the site.
- Liaising with the CDM co-ordinator regarding any design work.
It is important that the principal contractor is appointed as early as possible in order to allow them sufficient time to prepare the construction phase plan. The CDM planning period is a period allowed by the client to the principal contractor referred to in regulation 15(b) of the CDM regulations for planning and preparing for construction work.
[edit] Related articles on Designing Buildings Wiki
- CDM.
- CDM 2015 principal contractor.
- CDM client.
- CDM contractors.
- CDM co-ordinators.
- CDM designers.
- CDM planning period.
- CDM workers.
- Client.
- Construction phase plan.
- Contractor.
- Health and safety.
- Health and safety file.
- Notify HSE.
- Pre-construction information.
- Site induction.
- Site waste management plan.
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.




















