CDM 2007 principal contractor
For information about the role of the principal contractor under the 2015 CDM regulations see CDM 2015 principal contractor.
The text below relates to the superseded 2007 CDM regulations and is provided as a historical reference.
The Construction (Design and Management) Regulations (CDM Regulations) are intended to ensure health and safety issues are properly considered during a project’s development so the risk of harm to those who have to build, use and maintain structures is reduced.
They were introduced in 1994 and came into force on 31 March 1995. They were substantially revised in 2007.
The regulations impose duties on:
- The client. (See CDM client for more information)
- Designers. (See CDM designers for more information)
- The CDM co-ordinator.
- The principal contractor.
- Contractors. (See CDM contractors for more information)
- Workers. (See CDM workers for more information)
The regulations require that a principal contractor is appointed for all notifiable projects as soon as practicable and at the latest before construction works begin. Notifiable projects are those which last more than 30 days or involve 500 person days of construction work.
The CDM co-ordinator must inform the Health and Safety Executive of the appointment of the principal contractor.
The main contractor will usually be the principal contractor. The principal contractor's role is to plan, manage and co-ordinate health and safety during construction.
The duties of the principal contractor include:
- Preparing a construction phase plan (at least an initial construction phase plan for the early stages of the works must be prepared before construction work can begin).
- Providing contractors with information allowing them to work safely.
- Ensuring co-operation and co-ordination between parties involved in the works.
- Ensuring that other contractors identify, assess and manage risks.
- Ensuring that welfare facilities are in place.
- Ensuring that the workforce is inducted, informed, trained and consulted.
- Taking steps to prevent unauthorised access to the site.
- Displaying the required F10 notice on the site.
- Liaising with the CDM co-ordinator regarding any design work.
It is important that the principal contractor is appointed as early as possible in order to allow them sufficient time to prepare the construction phase plan. The CDM planning period is a period allowed by the client to the principal contractor referred to in regulation 15(b) of the CDM regulations for planning and preparing for construction work.
[edit] Related articles on Designing Buildings Wiki
- CDM.
- CDM 2015 principal contractor.
- CDM client.
- CDM contractors.
- CDM co-ordinators.
- CDM designers.
- CDM planning period.
- CDM workers.
- Client.
- Construction phase plan.
- Contractor.
- Health and safety.
- Health and safety file.
- Notify HSE.
- Pre-construction information.
- Site induction.
- Site waste management plan.
Featured articles and news
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.
The green jobs delivery group.
CIAT commentary after the first meeting.
Liverpool's world heritage site status
Who is to blame?
Research recommends focussing on portfolio success rather than project success.
ICE and BSI launch revised PAS 128 standard.
The revised standard for mapping underground utilities.
Launching the UK net zero carbon buildings standard.
Cross-industry steering group seeks support in delivery.
How to write an inspection and test plan.
Help us update process pieces from your field.
APM report explores existing practice.
Previous reflections on mental health with CIAT.
COVID-19 and the importance of mental wellbeing.
IHBC accreditation recognised by CSCS
As Professionally Qualified Person (PQP).
The Queens speech; bill by bill for 2022.
In order of relevance and with industry responses.
Mental Health awareness week, May 9-15.
Raising awareness of the impacts of loneliness.
Rapidly renewable materials and construction.
The list is growing, and in more ways than one.
Personal experiences of infrastructure maintenance issues.
We shouldn’t build new, If we can’t maintain what's built.
Mass timber: challenges and potential solutions.
Timber Accelerator Hub phase 1 report