Notifiable project F10 form
The Construction (Design and Management) Regulations 2015 (CDM regulations) require that the Health and Safety Executive (HSE) must be notified of any project defined as construction under the regulations where the construction work is likely to last longer than 30 working days and have more than 20 workers working simultaneously at any point in the project, or exceed 500 person days. This can be done using an F10 form.
Regulation 6 of the CDM regulations requires that the client must give notice in writing to the HSE as soon as is practicable before the construction phase begins, or arrange for someone else to do this on their behalf.
The notice must include the details included in schedule 1 of the regulations:
- The date of forwarding the notice.
- The address of the construction site or precise description of its location.
- The name of the local authority where the construction site is located.
- A brief description of the project and the construction work that it entails.
- The following contact details of the client: name, address, telephone number and (if available) an email address.
- The following contact details of the principal designer: name, address, telephone number and (if available) an email address.
- The following contact details of the principal contractor: name, address, telephone number and (if available) an email address.
- The date planned for the start of the construction phase.
- The time allocated by the client under regulation 4(1) for the construction work.
- The planned duration of the construction phase.
- The estimated maximum number of people at work on the construction site.
- The planned number of contractors on the construction site.
- The name and address of any contractor already appointed.
- The name and address of any designer already appointed.
- A declaration signed by or on behalf of the client that the client is aware of the client duties under these Regulations.
Where details are not available (such as the details of the principal contractor) they must be provided when they are available, and in any event, before construction works begin.
The notice must also be clearly displayed in the construction site office in a comprehensible form where it can be read by any worker engaged in the construction work; and if necessary, be periodically updated.
HSE will take 10 days to process notifications by manual form. (Ref. HSE, F10 Manual input form frequently asked questions.) However, notification can now be carried out online by filling out an e-form and manual notification forms will cease to be available after 31 March 2015. Confirmation of receipt of an e-F10 form should be received shortly after submission.
[edit] Related articles on Designing Buildings
- Accident book.
- Accident report.
- CDM.
- CDM for self-builders and domestic clients.
- Competent person.
- Fee for intervention.
- First aider.
- Health and safety.
- Health and Safety Executive.
- Health and safety inspector.
- Incident reporting system.
- Inspections focus on occupational lung disease.
- Licence for Alterations for Apartment.
- Principal contractor.
- Reporting accidents and injuries on construction sites.
- Site records and registers.
- What approvals are needed before construction begins.
[edit] External references.
- HSE How to notify a project.
- Schedule 1 of the CDM regulations.
Featured articles and news
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.
























Comments