Baseline programme
A baseline programme may be prepared by a contractor at the beginning of a project. This is a detailed view of how they will divide the works into activities, the duration of those activities, and logic links to preceding and succeeding activities. This programme should be practicable and realistic, showing when the contractor intends to carry out each part of the works and identifying the resources they intend to use.
Under NEC3 contracts, the contractor’s programme is then submitted to the project manager, and if the project manager accepts it, it becomes the ‘accepted programme’ identified in the contract data.
The contractor’s programme is likely to be updated throughout the course of the works and when accepted by the project manager, that updated programme becomes the new accepted programme.
NEC4 introduces the new concept of ‘treated acceptance’, by which the project manager has a specified period of time to notify the contractor whether their programme has been accepted or not. If they fail to notify the contractor within this period, the programme is deemed to be accepted.
NB The CIOB Planning Protocol 2021 (CIOB PP21), a technical information sheet published by the Chartered Institute of Building (CIOB) in February 2021, defines a baseline programme as: ‘A programme typically prepared prior to the commencement of a project, representing a contractor’s planned intention for sequencing the works. This programme is later used as a baseline for measuring the contractor’s actual progress and performance.’
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.