Main author
Multiple Author ArticleBREEAM Environmental management
Contents |
[edit] Aim and benefits
To encourage contractors, or the use of contractors, who operate environmental management systems and to ensure that their sites are managed in an environmentally responsible manner; implementing best practice pollution prevention policies and procedures.
[edit] When to consider
This issue should be considered prior to the selection of the contractor so that the requirement for the principal contractor to operate an environmental management system (EMS) can be included within the tender documents.
[edit] Step by step guidance
At the pre-assessment stage, the size, value and complexity of the project may have a bearing on whether the client wishes to target this issue. It should be ascertained whether the client would prefer not to limit the tendering process to those contractors holding EMS on simple buildings, where the use of a local, smaller builder (less likely to operate an EMS) may be more appropriate.
Where the principal contractor is not appointed at design stage, a commitment to appoint a contractor who operates an EMS such as ISO 14001 for their main construction operations and a requirement for the contractor to implement best practice pollution prevention policies and procedures on site in accordance with Pollution Prevention Guidelines, working at construction and demolition sites: PPG6 should be included within the tender contract documentation or within a formal letter of commitment from the client.
Once appointed, the principal contractor should provide a copy of their EMS certification or, for BS 8555 - evidence of their status such as copies of their phase one to four audits.
The contractor should provide relevant sections of their environmental management procedures manual to show that they have company policies in place. They should also maintain records to evidence the procedures in place on site were implemented. This could be in the form of drainage plans to show that the temporary site drainage was connected up correctly and that existing surface water gullies are protected from site pollution e.g. concrete washing out takes place away from the area. Site plans could be provided to show the location for the storage of hazardous liquids and fuels and photographic records kept to show that it was stored in double bunded tanks with spill kits to hand. The contractor should be made aware of the records required to be kept for the specific site prior to commencing on site.
[edit] Questions to ask while seeking compliance
- Does the contractor operate an EMS system?
- Are there any site-specific pollution issues that need to be addressed i.e. nearby watercourses or high ground water table?
[edit] Tools and resources
Construction and demolition sites, PPG6: prevention pollution provides guidance on how to prevent pollution and comply with environmental law at construction and demolition sites. This publication was withdrawn from use by the EA in December 2015 as the EA no longer provides "good practice" guidance. A copy can still be found on the national archives on the link below:
More information and an introduction to environmental management systems can be found at the links below:
- WRAP: Your Guide to Environmental Management Systems
- New Construction 2014 Knowledge Base link for Man03 Issues
- Non Domestic Refurbishment and Fit Out Knowledge Base link for Man03 Issues
- BREEAM UK New Construction 2014 Issue 5.0 - Man03
- BREEAM UK Refurbishment and Fit Out 2014 Issue 1.1 - Man03
[edit] Tips and best practice
It should be noted that for Healthcare projects, it is a pre-requisite that the principal contractor operates an EMS system.
Generally, principal contractors will hold third party certification to ISO 14001. However, small to medium contractors may opt for a more manageable staged approach to environmental management. To be compliant, the contractor must have completed the phased audit stages one to four and provide evidence to this effect.
[edit] Typical evidence
[edit] Design Stage
Design stage evidence can be awarded based on contract clauses/specifications to show a commitment by the client/developer to appoint a principal contractor who will operate the EMS and follow best practice pollution prevention policies and procedures. Where the contractor is selected, they should provide a copy of their EMS certification.
[edit] Post-construction stage
At post-construction stage, the principal contractor must provide a copy of their EMS certification, or for BS 8555 - evidence of their status (e.g. a copy of their phase 4 audit).
To show compliance with PPG 6, the contractor should provide a letter or report covering any actions completed together with supporting photographic evidence. They could also use drawings, company policies and method statements to show that works have been carried out and managed in an appropriate manner.
[edit] Applicable Schemes
The guidelines collated in this ISD aim to support sustainable best practice in the topic described. This issue may apply in multiple BREEAM schemes covering different stages in the life of a building, different building types and different year versions. Some content may be generic but scheme nuances should also be taken into account. Refer to the comments below and related articles to this one to understand these nuances. See this document for further guidelines.
- UK New Construction 2014
BRE Global does not endorse any of the content posted and use of the content will not guarantee the meeting of certification criteria.
--Multiple Author Article 16:23, 19 Apr 2018 (BST)
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.