Main author
Multiple Author ArticleBREEAM Environmental management
Contents |
[edit] Aim and benefits
To encourage contractors, or the use of contractors, who operate environmental management systems and to ensure that their sites are managed in an environmentally responsible manner; implementing best practice pollution prevention policies and procedures.
[edit] When to consider
This issue should be considered prior to the selection of the contractor so that the requirement for the principal contractor to operate an environmental management system (EMS) can be included within the tender documents.
[edit] Step by step guidance
At the pre-assessment stage, the size, value and complexity of the project may have a bearing on whether the client wishes to target this issue. It should be ascertained whether the client would prefer not to limit the tendering process to those contractors holding EMS on simple buildings, where the use of a local, smaller builder (less likely to operate an EMS) may be more appropriate.
Where the principal contractor is not appointed at design stage, a commitment to appoint a contractor who operates an EMS such as ISO 14001 for their main construction operations and a requirement for the contractor to implement best practice pollution prevention policies and procedures on site in accordance with Pollution Prevention Guidelines, working at construction and demolition sites: PPG6 should be included within the tender contract documentation or within a formal letter of commitment from the client.
Once appointed, the principal contractor should provide a copy of their EMS certification or, for BS 8555 - evidence of their status such as copies of their phase one to four audits.
The contractor should provide relevant sections of their environmental management procedures manual to show that they have company policies in place. They should also maintain records to evidence the procedures in place on site were implemented. This could be in the form of drainage plans to show that the temporary site drainage was connected up correctly and that existing surface water gullies are protected from site pollution e.g. concrete washing out takes place away from the area. Site plans could be provided to show the location for the storage of hazardous liquids and fuels and photographic records kept to show that it was stored in double bunded tanks with spill kits to hand. The contractor should be made aware of the records required to be kept for the specific site prior to commencing on site.
[edit] Questions to ask while seeking compliance
- Does the contractor operate an EMS system?
- Are there any site-specific pollution issues that need to be addressed i.e. nearby watercourses or high ground water table?
[edit] Tools and resources
Construction and demolition sites, PPG6: prevention pollution provides guidance on how to prevent pollution and comply with environmental law at construction and demolition sites. This publication was withdrawn from use by the EA in December 2015 as the EA no longer provides "good practice" guidance. A copy can still be found on the national archives on the link below:
More information and an introduction to environmental management systems can be found at the links below:
- WRAP: Your Guide to Environmental Management Systems
- New Construction 2014 Knowledge Base link for Man03 Issues
- Non Domestic Refurbishment and Fit Out Knowledge Base link for Man03 Issues
- BREEAM UK New Construction 2014 Issue 5.0 - Man03
- BREEAM UK Refurbishment and Fit Out 2014 Issue 1.1 - Man03
[edit] Tips and best practice
It should be noted that for Healthcare projects, it is a pre-requisite that the principal contractor operates an EMS system.
Generally, principal contractors will hold third party certification to ISO 14001. However, small to medium contractors may opt for a more manageable staged approach to environmental management. To be compliant, the contractor must have completed the phased audit stages one to four and provide evidence to this effect.
[edit] Typical evidence
[edit] Design Stage
Design stage evidence can be awarded based on contract clauses/specifications to show a commitment by the client/developer to appoint a principal contractor who will operate the EMS and follow best practice pollution prevention policies and procedures. Where the contractor is selected, they should provide a copy of their EMS certification.
[edit] Post-construction stage
At post-construction stage, the principal contractor must provide a copy of their EMS certification, or for BS 8555 - evidence of their status (e.g. a copy of their phase 4 audit).
To show compliance with PPG 6, the contractor should provide a letter or report covering any actions completed together with supporting photographic evidence. They could also use drawings, company policies and method statements to show that works have been carried out and managed in an appropriate manner.
[edit] Applicable Schemes
The guidelines collated in this ISD aim to support sustainable best practice in the topic described. This issue may apply in multiple BREEAM schemes covering different stages in the life of a building, different building types and different year versions. Some content may be generic but scheme nuances should also be taken into account. Refer to the comments below and related articles to this one to understand these nuances. See this document for further guidelines.
- UK New Construction 2014
BRE Global does not endorse any of the content posted and use of the content will not guarantee the meeting of certification criteria.
--Multiple Author Article 16:23, 19 Apr 2018 (BST)
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.