Production information report for design and construction
The production information report is a work stage report produced by the consultant team for the client at the end of the production information stage (see free work plans on the Designing Buildings Wiki home page).
It is the last opportunity for the client to consider issues to do with the design of the development and the form of contract before the tender process begins. It may also be the first time that the client has seen drawings describing key components (such as door handles), assemblies and specialist items. As a result, the client may wish to issue the production information report (or parts of it) for consideration to key users (or user panels) and perhaps to their lawyer or other independent client advisers. Once the main contractor has been appointed, subsequent changes can become very expensive.
The production information report may include:
- The approximate quantities cost plan and cash flow projection.
- Packaging strategy (and costs associated with individual packages).
- An assessment of cost uncertainty and the reasons for this.
- Identification of provisional sums.
- A schedule of outstanding information (including any client contributions that will be required for the contract documents).
- A schedule of outstanding consents (such as statutory approvals or planning conditions).
- A description of proposed preliminaries and other items to bring to the client's attention.
- Proposed warranties and bonds.
- The proposed form of contract, contract conditions and any proposed changes to the contract.
- Proposed treatment of liquidated damages.
- A schedule of exclusions from the contract.
- Any insurance issues.
- Drawings and specifications describing key components, assemblies and specialist items.
- A list of any remaining components, assemblies, specialist items, samples or materials still requiring approval by client.
- An assessment of the possible use of preliminary contracts.
- An assessment of the possibility of ordering long-lead items early.
- The proposed date of possession.
- Tender procedures and the tender period.
- An assessment of the need to appoint site inspectors.
- An assessment of the need to appoint party wall surveyor(s).
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.

















Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.