Indirect costs in construction
Indirect costs (or indirect spend) are those costs that are necessary to keep a process or project running, but which do not vary directly with the volume of goods or services produced and are not easily attributable to a particular process or project. This might for example include; rent, insurance, advertising and marketing and so on. These types of indirect costs may be referred to as overheads.
This is as opposed to direct costs, which are those costs incurred directly by production and include items such as raw materials, labour, equipment, power and so on. Direct costs can be traced and are attributed to a cost ‘object’ which may be a product, department, cost centre or project.
So, indirect costs do not vary directly with production levels, whereas direct costs remain dependent on production levels and will vary when production is increased or decreased.
NB Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines indirect costs as: ‘…costs incurred during construction works that cannot be attributed to any one section of the works; they may be fixed (e.g. the cost of bringing accommodation to the site) or time-related (e.g. the cost of insurance or security personnel).’
For more information see: Direct costs.
[edit] Related articles on Designing Buildings
Featured articles and news
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.



















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
I would like to know if prelim, overheads and profits are considered as "indirect costs"
They are typically considered to be indirect costs.