Time and cost management contract suite
![]() |
[edit] Introduction
The Time and Cost Management Contract is a revised edition of what was previously the CIOB’s Complex Projects Contract, published in 2013. The name has been changed to reflect more clearly the core strengths of the Contract. The Time and Cost Management Contract is written for use with the Time and Cost Management Contract suite’s Subcontract and Consultancy Appointment to provide a uniform approach to time, cost and risk management from initiation to completion of building and engineering projects.
[edit] Use of the contract
The contract is most suitable for those projects which cannot effectively be managed intuitively and which require for their success a more scientific approach to time- and cost-risk management than is usual on more simple projects. The contract can be used by companies, public authorities and private individuals in the UK and in any other country requiring the contractor to build only from a design prepared under the direction of the employer, or for the contractor to design the works in whole or in part.
The contract can be used for:
- Build-only of a design prepared under the direction of the employer;
- Build-only of a design prepared under the direction of the employer, but with the contractor’s design of parts;
- Design-and-build or turnkey projects in which the contractor is responsible for both the design and construction of the works, and
- Construction management and management contracting (with some changes in terms required by special conditions).
[edit] Pricing
The contract can be used with any method of pricing. Commonly, this includes fixed price, target cost, measured term, fixed fee, cost reimbursement, partnering and alliancing. The required method of pricing is to be described in the special conditions.
[edit] Special conditions
The standard documentation is expected to be supplemented by special conditions setting out the method of pricing, insurance requirements, bonding and any other matter peculiar to the particular project for which it is used. The special conditions take priority over these standard conditions.
[edit] Specification
The standard documentation is expected to be supplemented by a contract specification identifying the standards of performance required for the particular project.
[edit] Time management
The contract requires competence in critical-path network modelling, resource allocation and productivity analysis. The working schedule is required to be in differing densities, updated and revised on the rolling-wave principle that constantly predicts the currently attainable completion date, sectional completion dates and key dates.
[edit] Cost management
Cost management is by reference to the values attributed to the activities in the working schedule with progress updated from databased progress records. The updated working schedule constantly predicts the out-turn cost of the works and the value of work done to date.
[edit] Risk management
The contract is a collaborative contract requiring the contractor, its subcontractors and the design consultants to work with the time manager, cost manager, contract administrator and the employer to constantly appraise risk and to confer in taking practical action to overcome and avoid unnecessary consequences of time and cost risks. The time manager is required to collaborate with the contractor, subcontractors and consultants. The contract contains power to instruct acceleration both to overcome the effects of a delay to progress and bring forward completion dates where practical.
[edit] Collaboration
The contract requires a collaborative approach to design in conformity with British Standards Institution’s BS 1192:2007, but goes further in expressly requiring the contractor and all subcontractors and consultants having a continuing role in design, administration or quality control during the works to participate in decision making, quality control, time management, cost management and risk management.
[edit] Building Information Modelling (BIM)
The contract is suitable for Level 2 Projects 1 and the collaborative production of information throughout the project lifecycle. It is compatible with the requirements of the British Standards Institution’s PAS 1192: Part 2, 2013 ‘Specification for information management for the capital/delivery phase of construction projects using building information modelling’ and it may be used with any desired building information modelling protocol.
[edit] Information transfer
The contract requires information to be transferred electronically either by readable file or in native file format and in accordance with a file transfer protocol compatible with the British Standards Institution’s PAS 1192:4 2014 COBie.
[edit] Standard documentation
The suite comprises:
- Document No. 1, Contract Agreement, 2015 Edition
- Document No. 2, Contract Conditions, 2015 Edition
- Document No. 3, Contract Appendices, 2015 Edition
- Document No. 4, Subcontract Agreement, 2015 Edition
- Document No. 5, Subcontract Conditions, 2015 Edition
- Document No. 6, Subcontract Appendices, 2015 Edition
- Document No. 7, Consultancy Appointment, 2015 Edition
- Document No. 8, Schedules 8 and 9 for the appointment of the Time Manager, 2015 Edition
- Document No. 9, Schedules 8 and 9 for the appointment of the Contract Administrator, 2015 Edition
- Document No. 10 User Notes.
--CIOB
[edit] About this article
This article was first published on the website of the CIOB and can be accessed here. It also includes an interview with CIOB president Chris Chivers who talks about the Time and Cost Management Contract Suite in more detail.
[edit] Related articles on Designing Buildings Wiki
- A new theory for managing large complex projects.
- BIM.
- CIOB.
- Collaborative practices.
- Contractor's working schedule.
- FIDIC.
- Flagship first project for CPC 2013.
- JCT.
- NEC3.
- Procurement route.
- Time and Cost Management Contract (TCM15).
[edit] External references
Featured articles and news
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.