Query sheet in construction
The term ‘taking off’ refers to the process of identifying elements of construction works that can be measured and priced to produce bills of quantities. Analysis of drawings and specifications allows the cost consultant (usually a quantity surveyor) to prepare a taking off list, which lists all of the individual elements that comprise the works. These elements can then be measured in number, length, area, volume, weight or time and then collated and structured to produce an unpriced bill of quantities.
Taking off requires that the design is complete and a specification has been prepared. Where there may be uncertainty about specific elements of the design drawings and specifications, for example, there may be doubt about the nature, extent or dimensions of elements, these may be entered onto a query sheet and issued to the appropriate members of the consultant team for clarification.
Typically, a query sheet will show the quantity surveyor’s questions on one side and the consultant's answers on the other. These answers may include sketches and other information. Query sheets provide a formal record of questions that have been asked and answers given and should also record who asked each question, and when, and who answered each question, and when.
[edit] Related articles on Designing Buildings Wiki
- Approximate bill of quantities.
- Approximate quantities cost plan.
- Bill of quantities.
- Common Arrangement of Work Sections (CAWS).
- Comparison of SMM7 with NRM2.
- Computers in tendering.
- Construction work packaging.
- Contract documents
- Cost plans.
- Elemental cost plan.
- New Rules of Measurement.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender.
- Tender documentation.
- Tender pricing document.
- Uniclass.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.