Self-build home: project plan
This is a free-to-use, open-access plan for the organisation, design and construction of self-build homes.
If you have ideas for things to add to the plan, you can either edit the plan and add them yourself, or submit a comment and we will add them for you.
There are a number of delivery routes for self-build homes:
- Purchase a kit house.
- Appoint a design and build contractor to design and build the home.
- Appoint consultants to design the home then get a contractor to build it.
- Appoint consultants to design the home then manage the construction yourself.
It may not be clear which route should be followed until initial assessments have been carried out, a plot located and a brief prepared. See: Develop a delivery strategy for more information.
It is also possible to work with other organisations such as social landlords, developers, or community groups to develop a self-build home, however, these projects are likely to follow a plan imposed by the lead organisation and so they are not covered here, although many of the project stages will be similar. Working with a developer is sometimes called ‘custom build’ rather than ‘self build’.
See Custom-build home for more information.
An outline project plan is presented below. It describes activities step-by-step from the first moment it becomes apparent a self-build home could be a possibility right through to occupation of the completed building. Most of the stages are common to all four self-build routes, but the appointment stages vary.
Clicking on any of the stages will take you to a detailed description of the tasks that need to be carried out.
Stage 1: Justify the project.
Stage 2: Prepare a brief.
Stage 3: Find a plot.
Stage 4: Develop a delivery strategy.
Stage 5: Raise finance.
Stage 6: Acquire the plot.
Stage 7: Appoint designers.
- Appoint consultants to design the home, or;
- Appoint a contractor to design the home, or;
- Appoint a supplier to design a kit house.
Stage 8: Prepare a concept design.
Stage 9: Submit a planning application.
Stage 10: Prepare a detailed design.
Stage 11: Submit a building regulations application.
Stage 12: Prepare production information.
Stage 13: Appoint contractors.
- Appoint a contractor to construct the home, or;
- Appoint a range of contractors and suppliers to construct the home, or;
- Confirm appointment of the design and build contractor to construct the home, or;
- Confirm appointment of the supplier to fabricate and install the kit house.
Stage 14: Prepare for construction.
Stage 16: Construction.
Stage 17: Occupy the home and rectify any defects.
Featured articles and news
BSRIA Sentinel Clerk of Works Training Case Study
Strengthening expertise to enhance service delivery with integrated cutting-edge industry knowledge.
Impact report from the Supply Chain Sustainability School
Free sustainability skills, training and support delivered to thousands of UK companies to help cut carbon.
The Building Safety Forum at the Installershow 2025
With speakers confirmed for 24 June as part of Building Safety Week.
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Comments
It seems that the handover information such as building manual, H&S files, and other operation and maintenance documents are not mentioned here.
Not surpised that most building owners do not know what is in their building.