Precedence diagram method
The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB) in 2009 suggests that the term ‘precedence diagram method’, or PDM, refers to:
A method of constructing a logic network using nodes to represent the activities and connecting them by lines that show dependencies.
The Precedence Diagramming Method (PDM) is a visual representation technique which is used to prepare the project schedule network diagrams and determine the critical path.
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, suggest that a precedence diagram is a network in which the nodes symbolise activities, also referred to as an 'activity-on-the-node network'.
[edit] Related articles on Designing Buildings Wiki
- Acceleration.
- Accepted programme.
- Activity schedule.
- Contractor's master programme.
- Critical path method.
- Design programme.
- Gantt chart.
- Information release schedules.
- Milestones.
- Programme consultant.
- Programme float.
- Programme for building design and construction
- Scheduling construction activities.
- Short period programme.
- Time-location chart.
[edit] External references
Featured articles and news
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
Comments
Will any one answer me if I post a comment
That depends what the comment is.