Precedence diagram method
The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB) in 2009 suggests that the term ‘precedence diagram method’, or PDM, refers to:
A method of constructing a logic network using nodes to represent the activities and connecting them by lines that show dependencies.
The Precedence Diagramming Method (PDM) is a visual representation technique which is used to prepare the project schedule network diagrams and determine the critical path.
The Society of Construction Law Delay and Disruption Protocol, 2nd edition, suggest that a precedence diagram is a network in which the nodes symbolise activities, also referred to as an 'activity-on-the-node network'.
[edit] Related articles on Designing Buildings Wiki
- Acceleration.
- Accepted programme.
- Activity schedule.
- Contractor's master programme.
- Critical path method.
- Design programme.
- Gantt chart.
- Information release schedules.
- Milestones.
- Programme consultant.
- Programme float.
- Programme for building design and construction
- Scheduling construction activities.
- Short period programme.
- Time-location chart.
[edit] External references
Featured articles and news
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.






















Comments
Will any one answer me if I post a comment
That depends what the comment is.