Key dates
The New Engineering Contract (NEC) was first published in 1993 by the Institution of Civil Engineers. It is a suite of construction contracts that includes the Engineering and Construction Contract (ECC) intended to promote partnering and collaboration between the contractor and client. It was developed as a reaction to other more traditional forms of construction contract which were portrayed by some as adversarial.
The second edition, NEC2 contained contractual milestones for sectional completion as well as the final completion date. However, this was seen as limiting the ability of the Employer to add time constraints without having to take possession of section of works themselves. As a result, the third edition, NEC3 published in 2005 and introduced ‘key dates’.
Key dates are covered in ECC Clause 31.2 – Programme Requirements. The key dates provision is applicable when the Employer requires specific milestones or conditions to be completed or met by a certain date.
It defines a key date as:
‘…the date on which work is to meet the Conditions stated. The key date is the key date stated in the Contract Data and the Condition is the condition stated in the Contract Data unless later changed in accordance with this contract.’
Under sectional completion, the Employer must take over the works not later than two weeks after completion, whereas key dates simply require that the contractor meets defined conditions before the key date. An example of a key date could be the requirement for a subcontractor to have completed a section of works so that an electrical contractor can begin their work.
Key dates are contained in Contract Data (P1) and should be identified at the tender stage unless it has been agreed that they will be added mid-contract.
NEC3’s Guidance Notes state that key dates are applicable on projects with two or more contractors. They may have separate contracts but will have the same employer and, in most circumstances, the same project manager. The inclusion of key dates allows for closer cooperation and more efficient progress of the work as timescales can be planned in accordance with an overall project programme.
Should a contractor fail to meet the stated condition by the relevant key date, they may be liable to pay unliquidated (i.e. actual rather than pre-determined) damages to the Employer for additional costs incurred in carrying out the work or paying additional amounts to others. Because this risk is difficult to quantify, it is particularly important that the contractor manages the programme effectively and, if necessary, uses the early warning and compensation event processes provided for by the contract to notify of a potential delay to the works.
Criticism of the key dates provision focuses on the idea that precise identification of the conditions that are less than a sectional completion but must be done in order for a contractor to achieve a key date are often ambiguous and unclear.
NB The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK) suggests that 'key dates' are '...used to describe a date by which an identifiable accomplishment must be started or finished. Examples include ‘power on’, ‘weather-tight’ or the start or completion of phases of construction or of phases or sections of the contract, or completion of the works.'
[edit] Related articles on Designing Buildings
- Accepted programme.
- Bill of quantities.
- Compensation event.
- Construction contract.
- Contract conditions.
- Cost reimbursable contract.
- Delay damages.
- Electrical contractor.
- FIDIC.
- JCT.
- Latham Report.
- Line of balance (LOB).
- Milestones.
- NEC3.
- NEC contract change management systems.
- OGC.
- Topping out.
- Z clauses.
[edit] External references
- Fenwick Elliott – Contract of the future
Featured articles and news
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
























Comments