Key dates
The New Engineering Contract (NEC) was first published in 1993 by the Institution of Civil Engineers. It is a suite of construction contracts that includes the Engineering and Construction Contract (ECC) intended to promote partnering and collaboration between the contractor and client. It was developed as a reaction to other more traditional forms of construction contract which were portrayed by some as adversarial.
The second edition, NEC2 contained contractual milestones for sectional completion as well as the final completion date. However, this was seen as limiting the ability of the Employer to add time constraints without having to take possession of section of works themselves. As a result, the third edition, NEC3 published in 2005 and introduced ‘key dates’.
Key dates are covered in ECC Clause 31.2 – Programme Requirements. The key dates provision is applicable when the Employer requires specific milestones or conditions to be completed or met by a certain date.
It defines a key date as:
‘…the date on which work is to meet the Conditions stated. The key date is the key date stated in the Contract Data and the Condition is the condition stated in the Contract Data unless later changed in accordance with this contract.’
Under sectional completion, the Employer must take over the works not later than two weeks after completion, whereas key dates simply require that the contractor meets defined conditions before the key date. An example of a key date could be the requirement for a subcontractor to have completed a section of works so that an electrical contractor can begin their work.
Key dates are contained in Contract Data (P1) and should be identified at the tender stage unless it has been agreed that they will be added mid-contract.
NEC3’s Guidance Notes state that key dates are applicable on projects with two or more contractors. They may have separate contracts but will have the same employer and, in most circumstances, the same project manager. The inclusion of key dates allows for closer cooperation and more efficient progress of the work as timescales can be planned in accordance with an overall project programme.
Should a contractor fail to meet the stated condition by the relevant key date, they may be liable to pay unliquidated (i.e. actual rather than pre-determined) damages to the Employer for additional costs incurred in carrying out the work or paying additional amounts to others. Because this risk is difficult to quantify, it is particularly important that the contractor manages the programme effectively and, if necessary, uses the early warning and compensation event processes provided for by the contract to notify of a potential delay to the works.
Criticism of the key dates provision focuses on the idea that precise identification of the conditions that are less than a sectional completion but must be done in order for a contractor to achieve a key date are often ambiguous and unclear.
NB The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK) suggests that 'key dates' are '...used to describe a date by which an identifiable accomplishment must be started or finished. Examples include ‘power on’, ‘weather-tight’ or the start or completion of phases of construction or of phases or sections of the contract, or completion of the works.'
[edit] Related articles on Designing Buildings
- Accepted programme.
- Bill of quantities.
- Compensation event.
- Construction contract.
- Contract conditions.
- Cost reimbursable contract.
- Delay damages.
- Electrical contractor.
- FIDIC.
- JCT.
- Latham Report.
- Line of balance (LOB).
- Milestones.
- NEC3.
- NEC contract change management systems.
- OGC.
- Topping out.
- Z clauses.
[edit] External references
- Fenwick Elliott – Contract of the future
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Comments