Public project: occupation and defects liability period
The occupation and defects liability period follows practical completion. It is the stage after the client has taken possession of the development for occupation when any defects are rectified and the final certificate is issued signifying that the construction works have been fully completed (although on some projects, the integrated supply team may go on to operate the development). As the development is now occupied, close co-operation is required between the integrated supply team and the client so as so not to disturb occupants.
Depending on how experienced the client is, they may appoint external consultants to assist them. This means that some of the tasks attributed to the client below might actually be carried out by independent client advisers, a project manager or a contract administrator (employer's agent on design and build projects) and vice versa.
[edit] Starting the work stage.
The integrated supply team arranges a start-up meeting to plan the work stage.
The client may identify a requirement to appoint additional independent client advisers.
[edit] Rectifying defects.
We attribute contract administration tasks (such as making payments under the construction contract) to a contract administrator. Under some forms of procurement (such as design and build) the contract administrator (sometimes referred to as the employer's agent) will work for the client, however, on private finance initiative (PFI) projects, the client will not be a party to the construction contract and will not make payments for construction. Instead, the body funding the integrated supply team (perhaps a special purpose vehicle (SPV)) will take on the role of client for the construction contract and so they may appoint the contract administrator.
If the contract allows, the contract administrator may review all relevant events that might be considered to have affected the completion date and may adjust the completion date accordingly.
The client reports any defects in the works to the contract administrator (or integrated supply team). On large projects the integrated supply team may set up a hot desk for responding to any complaints or provide assistance required by the incoming occupants. The integrated supply team and client agree a programme for rectifying defects in a way that minimises disruption to the client.
If rectification works are significant, it may be necessary to re-appoint the principal designer (whose appointment may have terminated on certification of practical completion) and it may be necessary to co-ordinate amendments to the health and safety file.
If any amounts are due to the integrated supply team, they prepare interim applications for payment. The contract administrator checks applications for payment and issues interim certificates (payment notices).The notices must be issued within five days of the dates for payment set out in the contract. If any amounts are to be withheld, a pay less notice must be issued giving notice of the amount that will be paid and the basis for its calculation. The client (or funder) makes interim payments by the final date for payment.
At the end of the defects liability period, the contract administrator arranges inspections of the works and prepares a schedule of defects which is issued to the integrated supply team. The contract administrator agrees the programme for rectification of items on the schedule of defects with the client and integrated supply team.
The integrated supply team rectifies items listed on the schedules of defects and informs the contract administrator. The contract administrator arranges final inspections of the works and if satisfied issues the certificate of making good defects.
If a site waste management plan has been prepared, the integrated supply team may reconcile the planned handling of waste (as described in the site waste management plan) against what actually happened and provide an explanation of any differences.
[edit] Issuing the final certificate.
The integrated supply team co-ordinates the preparation of a final report and issues this to the client (or funder).
The client (or funder) and integrated supply team agree the final account. The contract administrator checks the final account and issues the final certificate (payment notice). If any amounts are to be withheld, a pay less notice must be issued giving notice of the amount that will be paid and the basis for its calculation.
The client (or funder) makes payment by the final date for payment (this will include the release of any remaining retention).
Issuing the final certificate may signify the end of the independent client advisers appointments. If post-occupancy evaluation services are required, these may require a new appointment.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.
























