Public project: occupation and defects liability period
The occupation and defects liability period follows practical completion. It is the stage after the client has taken possession of the development for occupation when any defects are rectified and the final certificate is issued signifying that the construction works have been fully completed (although on some projects, the integrated supply team may go on to operate the development). As the development is now occupied, close co-operation is required between the integrated supply team and the client so as so not to disturb occupants.
Depending on how experienced the client is, they may appoint external consultants to assist them. This means that some of the tasks attributed to the client below might actually be carried out by independent client advisers, a project manager or a contract administrator (employer's agent on design and build projects) and vice versa.
[edit] Starting the work stage.
The integrated supply team arranges a start-up meeting to plan the work stage.
The client may identify a requirement to appoint additional independent client advisers.
[edit] Rectifying defects.
We attribute contract administration tasks (such as making payments under the construction contract) to a contract administrator. Under some forms of procurement (such as design and build) the contract administrator (sometimes referred to as the employer's agent) will work for the client, however, on private finance initiative (PFI) projects, the client will not be a party to the construction contract and will not make payments for construction. Instead, the body funding the integrated supply team (perhaps a special purpose vehicle (SPV)) will take on the role of client for the construction contract and so they may appoint the contract administrator.
If the contract allows, the contract administrator may review all relevant events that might be considered to have affected the completion date and may adjust the completion date accordingly.
The client reports any defects in the works to the contract administrator (or integrated supply team). On large projects the integrated supply team may set up a hot desk for responding to any complaints or provide assistance required by the incoming occupants. The integrated supply team and client agree a programme for rectifying defects in a way that minimises disruption to the client.
If rectification works are significant, it may be necessary to re-appoint the principal designer (whose appointment may have terminated on certification of practical completion) and it may be necessary to co-ordinate amendments to the health and safety file.
If any amounts are due to the integrated supply team, they prepare interim applications for payment. The contract administrator checks applications for payment and issues interim certificates (payment notices).The notices must be issued within five days of the dates for payment set out in the contract. If any amounts are to be withheld, a pay less notice must be issued giving notice of the amount that will be paid and the basis for its calculation. The client (or funder) makes interim payments by the final date for payment.
At the end of the defects liability period, the contract administrator arranges inspections of the works and prepares a schedule of defects which is issued to the integrated supply team. The contract administrator agrees the programme for rectification of items on the schedule of defects with the client and integrated supply team.
The integrated supply team rectifies items listed on the schedules of defects and informs the contract administrator. The contract administrator arranges final inspections of the works and if satisfied issues the certificate of making good defects.
If a site waste management plan has been prepared, the integrated supply team may reconcile the planned handling of waste (as described in the site waste management plan) against what actually happened and provide an explanation of any differences.
[edit] Issuing the final certificate.
The integrated supply team co-ordinates the preparation of a final report and issues this to the client (or funder).
The client (or funder) and integrated supply team agree the final account. The contract administrator checks the final account and issues the final certificate (payment notice). If any amounts are to be withheld, a pay less notice must be issued giving notice of the amount that will be paid and the basis for its calculation.
The client (or funder) makes payment by the final date for payment (this will include the release of any remaining retention).
Issuing the final certificate may signify the end of the independent client advisers appointments. If post-occupancy evaluation services are required, these may require a new appointment.
Featured articles and news
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.