Progress of construction works
Most construction contracts will include a date by which the works described in the contract must be completed. This is either by means of a defined completion date, or a commencement date and a specified period for the works. This date may be varied during the works, for example if an extension of time is granted, or if the works are accelerated.
If no date or period is defined, a term will be implied that the contractor must complete the works in a reasonable time, that is, the time it would ordinarily take, plus an allowance for any extraordinary circumstances.
Unless the contract includes express provisions requiring that the works are carried out in a particular way, the contractor can achieve the completion date in whatever manner they choose, for example, by starting slowly and then speeding up, or by working sporadically. There is no implied term requiring that the works are carried out to a specific timetable.
However, many contracts include express terms requiring that the contractor proceeds ‘regularly and diligently’ with the works, irrespective of whether they are likely to achieve the completion date. They cannot work sporadically, or slow down if it becomes apparent that they will beat the completion date. Sub-contracts may include similar obligations, requiring sub-contractor progress to be reasonably in accordance with the progress of the main contract.
The term ‘time at large’ refers to a situation in which there is no date for completion, or where the date for completion has become invalid. The contractor is then no longer bound by the obligation to complete the works by a certain date. They may however still be bound by an obligation to proceed regularly and diligently or to complete the works within a reasonable time.
Designing Buildings Wiki includes a number of articles providing more information about construction progress and its measurement:
- Acceleration.
- Accepted programme.
- Activity schedule.
- Base date.
- Benchmarking.
- Completion date.
- Construction progress meeting.
- Construction progress report.
- Contractor's master programme.
- Critical path method.
- Design programme.
- Earned value analysis.
- Extension of time.
- Fast track construction.
- Gantt chart.
- How progress is agreed in construction.
- Information release schedules.
- Key performance indicators.
- Lead time.
- Line of balance (LOB).
- Logistics management.
- Milestones.
- Pareto analysis.
- Phased construction works.
- Precedence diagram method.
- Productivity in building design and construction.
- Productivity in construction: Creating a framework for the industry to thrive.
- Programme consultant.
- Programme float.
- Programme for building design and construction.
- Project programme.
- Regularly and diligently.
- Scheduling construction activities.
- Short period programme.
- Tender works programme.
- Time-location chart.
- Time at large.
- Time is of the essence.
- Time management of construction projects.
[edit]
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.