Post project review of construction projects
A post project review may begin during the defects liability period, when the client first occupies the development (now called the 'rectification period' in Joint Contracts Tribunal (JCT) contracts).
A post project review is undertaken to evaluate the effectiveness and efficiency of the project delivery process. To undertake a post project review, it is important to seek the views of contractors, designers, suppliers and the client about how well the project was managed.
This may include assessments of how well the delivery of the project performed against key performance indicators such as:
- The quality of briefing documents.
- The effectiveness of communications.
- The performance of the entire project team.
- Quality issues.
- Health and safety issues.
- Certification.
- Variations.
- Claims and disputes.
- Collaborative practices.
An evaluation can then be made of what lessons can be learned from the approach taken and a lessons learned report prepared.
A wider 'post occupancy evaluation' may comprise two studies:
- A post project review to evaluate the project delivery process.
- An assessment of performance in use, to assess the extent to which business and design objectives have been satisfied, which may not begin until 6 to 12 months after occupation, as operations may not be properly established before then.
See Post occupancy evaluation and Performance in use for more information.
NB When the development is first occupied by the client, it is important to visit the site immediately to identify any issues that need to be addressed quickly. It can be beneficial to establish a help-desk and rapid response team to resolve issues as they arise (See articles on occupation and migration strategy).
[edit] Related articles on Designing Buildings Wiki
- BREEAM.
- Building performance metrics.
- Defects liability period.
- End of contract report.
- Energy performance certificates.
- Extended aftercare.
- Initial aftercare.
- OGC Gateway Review 5: Operations review & benefits realisation (or benefits evaluation)
- Migration strategy.
- Performance in use.
- Performance of exemplar buildings in use: Bridging the performance gap FB 78.
- Post occupancy evaluation (repeats some of the text in this article).
- Post opening project evaluation.
- Soft landings.
- Value added.
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.