Approximate bill of quantities
An approximate bill of quantities (sometimes referred to as a notional bill of quantities or provisional bill of quantities) can be used on projects where it is not possible to prepare a firm bill of quantities at the time of tendering.
Generally, the design will be relatively complete, but there is either insufficient time or information to determine the exact quantities and so a conventional bill of quantities cannot be prepared.
Tendering on the basis of an approximate bill of quantities can allow early selection of the contractor and so an early start on site. However, the approximate nature of the bill of quantities will tend to result in more variations during construction and so less price certainty when the investment decision is made. This means that even if it is not possible to determine exact quantities, it is sensible to try to ensure quantities are as accurate as possible.
Some contracts allow for re-measurement of approximate quantities (for example, this is common on cut-and-fill on roadworks). Here, quantities are simply revised and payments made accordingly without the need to instruct a variation.
If an approximate quantity turns out not to have been a realistic estimate of the quantity actually required, this may constitute a relevant event, giving rise to claims for an extension of time and loss and expense.
Approximate bills of quantities can also be used during the design process as a tool for controlling design costs (see approximate quantities cost plan below). They are then sometimes included in the tender documents as a guide with a caveat stating that responsibility for measuring quantities lies with the contractor, and drawings and specifications take priority over any description in the approximate bills.
An approximate quantities cost plan is, in effect, a priced approximate bill of quantities. It is a development of the elemental cost plan, but unlike the elemental cost plan (in which the cost of elements is broken down from the overall construction cost, based on the experience of the cost consultant and known costs of similar completed projects) the approximate quantities cost plan is a first attempt to measure defined quantities from drawings.
It presents a more accurate picture of where costs are distributed, in particular it draws to the attention of designers those elements of the design that are standard and those that are not - and as a consequence may be more expensive. The approximate quantities cost plan should form a solid base for an effective value engineering exercise. From the point that the approximate quantities cost plan has been approved, cost control can be introduced by treating changes as if they are variations.
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- Approximate bill of quantities vs approximate quantities cost plan.
- Approximate quantities cost plan.
- Bill of quantities.
- CAWS.
- Common mistakes in bill of quantities.
- Extension of time.
- Firm bill of quantities.
- Loss and expense.
- New Rules of Measurement.
- Packaging.
- Provisional sum.
- Relevant event.
- Standard Method of Measurement (SMM7).
- Types of bill of quantities.
- Unpriced bill.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.