Non-compliant tender
This article describes in detail the tender process for a typical commercial construction contract.
For a wider description of the range of tender processes that might be adopted on different types of project, see Tender processes.
For more information about different contractual procurement routes, see Procurement route.
An invitation to tender will generally include very specific requirements for the information and format of the tender that prospective suppliers must submit. This ensures that necessary information is included and that it is in a format that the client is able to analyse and compare with other tenders.
If a prospective contractor or supplier submits a tender that does not comply with the client's requirements then that bidder is said to have submitted a non-compliant bid. This can result in the tender being rejected. Full compliance requires that all material conditions of the invitation to tender must be complied with.
A tender may be non-compliant by:
- Not answering all the question(s).
- Exceeding the required word length.
- Submitting in the wrong format e.g PDF when Excel or Word were required.
- Making a late submission.
- Not breaking down information in the correct way.
- Submitting proposals that do not comply with the client's requirements.
However, a non-compliant proposal, sometimes referred to as a variant bid, may be submitted intentionally if the tenderer believes that an alternative could offer better value for money that the requirements set out in the invitation to tender. However, non-compliant proposals should only be submitted if they have been requested or are explicitly permitted by the client, and they may need to be accompanied by a compliant bid to allow direct comparison with other tenders.
See also: Qualified bid.
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Bid writer.
- Competitive tender.
- Contract award.
- Contract conditions.
- Contract documents.
- Due diligence when selecting contractors or subcontractors.
- Invitation to tender.
- Letter of award.
- Mid-tender interview.
- Most Economically Advantageous Tender (MEAT).
- Pre-tender interview.
- Procurement route.
- Qualified bid.
- Selection criteria.
- Tender documentation.
- Tender evaluation.
- Tender processes.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.