Management contract: occupation and defects liability period
The occupation and defects liability period is the stage after the client has taken possession of the development for occupation when any defects are rectified and the final certificate is issued signifying that the construction works have been fully completed. As the development is now occupied, close co-operation is required between the management contractor and the client so as so not to disturb occupants, whose activities will take priority over works contractors rectifying defects.
There are two different forms of contract operating during the defects liability period:
- The contract between the client and the management contractor. The client may have appointed a contract administrator to administer this contract.
- The contracts between the management contractor and each works contractor. These contracts are administered by the management contractor.
[edit] Starting the work stage.
The management contractor arranges a start-up meeting to plan the work stage.
On management contracts, a separate certificate of practical completion is issued for each works contract. This means that defects liability periods may be at different times for each works contract and as a consequence, the management contractor may continue to hold construction progress meetings and issue construction progress reports for continuing works contracts and may have to protect completed work from continuing work.
[edit] Rectifying defects.
If the contract allows, the management contractor may review all relevant events that might be considered to have affected the completion date for each works contract and may adjust their completion dates accordingly.
The client reports any defects in the works to the management contractor. On large projects the management contractor may set up a hot desk for responding to complaints or to provide assistance required by the incoming occupants. The management contractor takes advice on the action necessary to rectify the defects from the consultant team and the management contractor and client agree a programme for rectifying defects in a way that minimises disruption to the client.
If rectification works are significant, it may be necessary for the client to re-appoint the principal designer (whose appointment may have terminated on certification of practical completion) and it may be necessary to amend the health and safety file.
At the end of the defects liability period for each works contract, the management contractor arranges inspections of the works and prepares a schedule of defects which is issued to the works contractor. The management contractor agrees the programme for rectification of items on the schedule of defects with the client's contract administrator and works contractors, which should in any event be rectified within a reasonable time.
The works contractor rectifies items listed on the schedules of defects, informs the management contractor and provides the management contractor with information for the calculation of the final works contract sum.
The management contractor arranges final inspections of the works contractors works and if satisfied issues a final certificate (payment notice) for that works contract. If the management contractor intends to pay a different amount from that shown on the certificate, then they must issue a pay less notice giving the basis for the calculation of the amount they intend to pay. The management contractor makes payments to the works contractors by the final dates for payment. This may include the release of any remaining retention if applicable
The management contractor completes the building owner's manual.
If a site waste management plan has been prepared, the management contractor may reconcile the planned handling of waste against what actually happened and provide an explanation of any differences.
[edit] Issuing the final certificate.
Once the management contractor has received information from all works contractors enabling them to calculate the final works contract sum for each works contract, the management contractor provides the client's contract administrator (or cost consultant) with information allowing them to calculate the prime cost (the cost of the works contracts).
The management contractor co-ordinates preparation of the final report.
The client's contract administrator issues the final certificate (payment notice) under the management contractor's contract. The client makes payment to the management contractor by the final date for payment (this will include the release of any remaining retention).
The client's contract administrator co-ordinates preparation of a final report and issues this to the client.
Issuing the final certificate will normally signify the end of the management contractor's and consultant team's appointments. If post-occupancy evaluation services are required, these may involve a new appointment.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.