Management contract: occupation and defects liability period
The occupation and defects liability period is the stage after the client has taken possession of the development for occupation when any defects are rectified and the final certificate is issued signifying that the construction works have been fully completed. As the development is now occupied, close co-operation is required between the management contractor and the client so as so not to disturb occupants, whose activities will take priority over works contractors rectifying defects.
There are two different forms of contract operating during the defects liability period:
- The contract between the client and the management contractor. The client may have appointed a contract administrator to administer this contract.
- The contracts between the management contractor and each works contractor. These contracts are administered by the management contractor.
[edit] Starting the work stage.
The management contractor arranges a start-up meeting to plan the work stage.
On management contracts, a separate certificate of practical completion is issued for each works contract. This means that defects liability periods may be at different times for each works contract and as a consequence, the management contractor may continue to hold construction progress meetings and issue construction progress reports for continuing works contracts and may have to protect completed work from continuing work.
[edit] Rectifying defects.
If the contract allows, the management contractor may review all relevant events that might be considered to have affected the completion date for each works contract and may adjust their completion dates accordingly.
The client reports any defects in the works to the management contractor. On large projects the management contractor may set up a hot desk for responding to complaints or to provide assistance required by the incoming occupants. The management contractor takes advice on the action necessary to rectify the defects from the consultant team and the management contractor and client agree a programme for rectifying defects in a way that minimises disruption to the client.
If rectification works are significant, it may be necessary for the client to re-appoint the principal designer (whose appointment may have terminated on certification of practical completion) and it may be necessary to amend the health and safety file.
At the end of the defects liability period for each works contract, the management contractor arranges inspections of the works and prepares a schedule of defects which is issued to the works contractor. The management contractor agrees the programme for rectification of items on the schedule of defects with the client's contract administrator and works contractors, which should in any event be rectified within a reasonable time.
The works contractor rectifies items listed on the schedules of defects, informs the management contractor and provides the management contractor with information for the calculation of the final works contract sum.
The management contractor arranges final inspections of the works contractors works and if satisfied issues a final certificate (payment notice) for that works contract. If the management contractor intends to pay a different amount from that shown on the certificate, then they must issue a pay less notice giving the basis for the calculation of the amount they intend to pay. The management contractor makes payments to the works contractors by the final dates for payment. This may include the release of any remaining retention if applicable
The management contractor completes the building owner's manual.
If a site waste management plan has been prepared, the management contractor may reconcile the planned handling of waste against what actually happened and provide an explanation of any differences.
[edit] Issuing the final certificate.
Once the management contractor has received information from all works contractors enabling them to calculate the final works contract sum for each works contract, the management contractor provides the client's contract administrator (or cost consultant) with information allowing them to calculate the prime cost (the cost of the works contracts).
The management contractor co-ordinates preparation of the final report.
The client's contract administrator issues the final certificate (payment notice) under the management contractor's contract. The client makes payment to the management contractor by the final date for payment (this will include the release of any remaining retention).
The client's contract administrator co-ordinates preparation of a final report and issues this to the client.
Issuing the final certificate will normally signify the end of the management contractor's and consultant team's appointments. If post-occupancy evaluation services are required, these may involve a new appointment.
Featured articles and news
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.