Management contract: occupation and defects liability period
The occupation and defects liability period is the stage after the client has taken possession of the development for occupation when any defects are rectified and the final certificate is issued signifying that the construction works have been fully completed. As the development is now occupied, close co-operation is required between the management contractor and the client so as so not to disturb occupants, whose activities will take priority over works contractors rectifying defects.
There are two different forms of contract operating during the defects liability period:
- The contract between the client and the management contractor. The client may have appointed a contract administrator to administer this contract.
- The contracts between the management contractor and each works contractor. These contracts are administered by the management contractor.
[edit] Starting the work stage.
The management contractor arranges a start-up meeting to plan the work stage.
On management contracts, a separate certificate of practical completion is issued for each works contract. This means that defects liability periods may be at different times for each works contract and as a consequence, the management contractor may continue to hold construction progress meetings and issue construction progress reports for continuing works contracts and may have to protect completed work from continuing work.
[edit] Rectifying defects.
If the contract allows, the management contractor may review all relevant events that might be considered to have affected the completion date for each works contract and may adjust their completion dates accordingly.
The client reports any defects in the works to the management contractor. On large projects the management contractor may set up a hot desk for responding to complaints or to provide assistance required by the incoming occupants. The management contractor takes advice on the action necessary to rectify the defects from the consultant team and the management contractor and client agree a programme for rectifying defects in a way that minimises disruption to the client.
If rectification works are significant, it may be necessary for the client to re-appoint the principal designer (whose appointment may have terminated on certification of practical completion) and it may be necessary to amend the health and safety file.
At the end of the defects liability period for each works contract, the management contractor arranges inspections of the works and prepares a schedule of defects which is issued to the works contractor. The management contractor agrees the programme for rectification of items on the schedule of defects with the client's contract administrator and works contractors, which should in any event be rectified within a reasonable time.
The works contractor rectifies items listed on the schedules of defects, informs the management contractor and provides the management contractor with information for the calculation of the final works contract sum.
The management contractor arranges final inspections of the works contractors works and if satisfied issues a final certificate (payment notice) for that works contract. If the management contractor intends to pay a different amount from that shown on the certificate, then they must issue a pay less notice giving the basis for the calculation of the amount they intend to pay. The management contractor makes payments to the works contractors by the final dates for payment. This may include the release of any remaining retention if applicable
The management contractor completes the building owner's manual.
If a site waste management plan has been prepared, the management contractor may reconcile the planned handling of waste against what actually happened and provide an explanation of any differences.
[edit] Issuing the final certificate.
Once the management contractor has received information from all works contractors enabling them to calculate the final works contract sum for each works contract, the management contractor provides the client's contract administrator (or cost consultant) with information allowing them to calculate the prime cost (the cost of the works contracts).
The management contractor co-ordinates preparation of the final report.
The client's contract administrator issues the final certificate (payment notice) under the management contractor's contract. The client makes payment to the management contractor by the final date for payment (this will include the release of any remaining retention).
The client's contract administrator co-ordinates preparation of a final report and issues this to the client.
Issuing the final certificate will normally signify the end of the management contractor's and consultant team's appointments. If post-occupancy evaluation services are required, these may involve a new appointment.
Featured articles and news
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.