Main types of planning permission
Contents |
[edit] Introduction
Planning permission is the legal process of determining whether proposed developments should be permitted. Responsibility for planning lies with local planning authorities (usually the planning department of the district or borough council). The legislation, policy and guidance that underpins planning in England can be found on the government's National Planning Practice Guidance website.
Other than permitted developments, (which are considered to have insignificant impact), all developments require planning permission. The Town and Country Planning (General Permitted Development) Order 1995 sets out details for developments that might be permitted without requiring a planning application.
There are three main types of planning permission:
- Outline
- Reserved matters
- Full planning (or detailed planning) permission.
[edit] Outline
Outline planning permission is an application for undertaking a development in principle. The applicant can use it to find out whether their proposed development is likely to be approved by the planning authority before substantial costs are incurred developing a detailed design. Outline planning applications allow the submission of outline proposals, the details of which may be agreed as 'reserved matters' applications at a later stage (see below).
For more information see: Outline planning application
[edit] Reserved matters
Once outline planning consent has been obtained, the reserved matters stage is the follow-up which gives the applicant the opportunity to provide (usually within three years) more detail, including:
- The layout of buildings within the proposed development.
- The precise height, width and length of individual buildings.
- The appearance of buildings.
- Access to and within the site for vehicles, cycles and pedestrians.
- Landscape proposals.
The details of the reserved matters application must be in line with the outline approval, including any conditions attached to the permission. It may be necessary to reapply for outline or full planning permission if the proposals have changed significantly.
For more information see: Reserved matters.
[edit] Full planning (or detailed planning) permission
Where alteration or erection of buildings (or a change of use) is required, full planning permission is the most widely used option. It is made for developments that include building, engineering or other works, in, on, over or under land, or the making of any material change in the use of any buildings or other land.
A full planning application is made in detail, in one go – with no preliminary or outline stages – and consent, if granted, is for a limited time period. If the development does not begin within this period, the applicant must apply for a renewal of limited permission.
For more information see: Detailed planning application.
[edit] Others
Other types of planning consent that might be required include:
- Listed building consent
- Advertisement consent
- Lawful Development Certificate
- Prior approvals
- Removal/variation of conditions
- Discharge of conditions
- Consent under Tree Preservation Orders
- Notification of proposed works to trees in conservation areas
- Application for non-material amendments
[edit] Related articles on Designing Buildings Wiki
- Approved documents.
- Approved inspector.
- Building codes.
- Building control body.
- Building control performance standards.
- Building notice.
- Building Regulations Advisory Committee (BRAC).
- Building regulations completion certificate.
- Building regulations inspection.
- Building warrant (Scotland).
- Do the building regulations apply to existing buildings?
- Failure to comply with the building regulations.
- Full plans.
- How long it takes to get building regulations approval and how long it lasts.
- Independent review of the building regulations and fire safety.
- Planning permission.
- Scottish building standards.
- Standard Assessment Procedure.
- Statutory approvals.
- Statutory authorities.
- The Building Act.
- The difference between planning permission building regulations approval.
- Welsh building regulations.
- What approvals are needed before construction begins.
Featured articles and news
In major support package for small businesses.
Conservation and transformation
Reading Ruskin’s cultural heritage. Book review.
Renovating Union Chain Bridge.
AI tools for planning, design, construction and management
A long, continually expanding list, any more to add?
Robots in the construction industry
From cultural characterisations to construction sites.
Empowering construction with AI integration
New horizons with a human touch.
Key AI related terms to be aware of
With explanations from the UK government.
A Better Hiring Toolkit for construction
Tooling up to hire under best practice standards in the sector.
Recharging Electrical Skills in Wales
Step by step collaborative solutions.
Ireland budget announcement 2025
CIOB responds with positivity, criticism and clarity.
The continued ISG fall out, where to go?
Support for ISG contractors, companies and employees.
New HES national centre for traditional building retrofit
Announced as HES publishes survey results which reveal strong support for retrofit.
Retrofit of Buildings, a CIOB Technical Publication
Expected to become one of the largest activities in the global construction industry.
Scope determination appeals and the Building Safety Act
Process explained following release of appeals guidance.
The ECA industry focus video channel
Keeping update with the industry session by session.
Over 25 recorded informations sessions freely available..