How long it takes to get building regulations approval and how long it lasts
Contents |
[edit] Introduction
There are two types of building regulations application:
- Full plans application: Generally on larger, new-build projects, a 'full plans' application will be made, meaning that full details of the proposed building works are submitted for approval before the works are carried out.
- Building notice application: On smaller projects, or when changes are made to an existing building, approval may be sought by giving a 'building notice'. In this case, a building inspector will approve the works as they are carried out by a process of inspection. However, this leaves the client at risk that completed works might not be approved, resulting in remedial costs.
[edit] Full plans application
A decision should be received within five weeks for a full plans application. However, this may be extended to two months by agreement. It is necessary then to give the building control body two working days notice before commencing the works.
It is permissible to begin works before approval has been received, however, if the works are subsequently found not to comply with the building regulations, they may have to be altered or removed.
The approval lasts for three years, within which time the building work must commence, or a fresh application will be required. This can be very important given the speed at which the regulations change, meaning that a building which has been approved, but where construction has not begun, may need to be re-designed to satisfy the new regulations.
Once the construction works have commenced, and the building control body has undertaken a commencement inspection, the approval lasts indefinitely.
A completion certificate should be received within eight weeks of completion of the building work if it complies with the regulations.
[edit] Building notice application
Works under a building notice application may begin as soon as the notice has been accepted. This is usually within two days.
The notice is valid for three years, after which it will lapse if the building work has not commenced. Once the works have commenced, the notice lasts indefinitely.
No completion certificate is issued as no plans have been submitted.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.
More than 200 remarkable buildings added to SAVE’s Buildings at Risk register.
Government scraps pre-application consultation for Nationally Significant Infrastructure Projects.
Historic England and infrastructure
New projects offer opportunities for the historic environment and local communities.
Construction Management, 2 July
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.

















