Free issue material
The term "free issue material" refers to materials or equipment supplied by the client to the contractor to be incorporated into the construction project at no cost to the contractor. The client retains ownership of the free issue materials but the contractor is responsible for the care, custody, and control of the free issue materials once they are received. This includes handling, storage, and protection of the materials. Contractors might need to insure the free issue materials against risks like theft, damage, or loss while they are in their possession.
For example, a client commissioning the construction of a new office building decides to supply specialised lighting fixtures as free issue materials. The contractor receives these fixtures and is responsible for their proper installation. If any fixtures are damaged while in the contractor's custody, the contractor must address the issue, either through repair, replacement, or insurance claims.
The contract will usually specify the type, quantity, and quality of the materials to be provided by the client. The contract may also outline the timing and logistics of delivery to ensure materials are available when needed without causing delays to the project. If free issue materials are found to be defective or not up to the specified quality, the contractor may need to notify the client and seek replacements, potentially impacting project timelines.
The value of free issue materials is typically excluded from the contract sum but must be accounted for in the project's overall value and progress reporting.
Clients may secure better pricing for materials by purchasing directly or using preferred suppliers and they can ensure specific materials meeting their quality standards are used in the project. However, proper coordination is required to ensure materials are delivered on time and are compatible with the construction schedule, and contractors must provide suitable storage and security for the free issue materials to prevent damage or loss.
Contracts involving free issue materials should clearly define:
- The list of materials to be provided.
- Delivery schedules and responsibilities.
- Procedures for handling defects or shortages.
- Insurance and liability requirements.
[edit] Related articles on Designing Buildings
Featured articles and news
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.