Early contractor involvement
On traditional construction contracts, the client first appoints consultants to design the project in detail, and then a contractor is appointed to construct the works.
However, this can be seen to be a somewhat fragmented and adversarial project structure which does not give the contractor the opportunity to contribute to the development of the design that they will be required to construct.
Civil Engineering Procedure 7th Edition, published by the Institution of Civil Engineers (ICE) suggests that early contractor involvement (ECI) denotes ‘…a non-traditional procurement route, where a contractor’s skills are introduced early into a project to bring design ‘buildability’ and cost efficiencies to the pre-construction phase’.
Typically, early contractor involvement might be enabled by a two-stage tender process, used in the first stage to procure contractor involvement in the design process, and in the second stage to procure construction of the works. Other procurement routes, such as design and build, construction management, or management contracting might also allow a contractor to become involved in the design stage.
Early contractor involvement can enable the contractor to:
- Contribute to the design process.
- Build a better team-working ethic.
- Introduce innovations.
- Advise on buildability, sequencing, and construction risk.
- Advise on the packaging of the works.
- Advise on the selection of specialist contractors.
- Spend more time developing a construction strategy, recruiting staff, identifying partners and so on.
- Help develop the cost plan and construction programme.
- Help develop the method of construction.
- Obtain prices for work packages from sub-contractors or suppliers on a open-book basis.
- Prepare a site layout plan for the construction stage.
- Draft the preliminaries for specialist and trade contractor bid documents.
- Assist with planning applications on matters concerning the build phase, such as waste disposal, construction traffic movements and tree protection.
ECI is particularly well-suited to large or complex projects, but can be adopted on any project.
The use of a Pre-Construction Services Agreement (PCSA, sometimes referred to as Pre-Contract Services Agreements) can enable the client to employ a contractor before the main construction contract has commenced.
The NEC3 Engineering and Construction Contract (ECC) Options C and E also include provisions for early contractor involvement. See NEC early contractor involvement for more information.
Early contractor involvement may require that the contractor undertakes the early design stages themselves, or that they simply contribute to the design development which is undertaken by others. There can sometimes be a degree of ambiguity about precisely what the contractor is expected to do in these stages, and this can cause confusion and dissatisfaction.
Another perceived disadvantage of early contractor involvement is that the contractor becomes involved in the project before it has been designed in detail, and so they are unable to give an accurate price for the construction works. While contracts generally provide for some element of transparency and competition in the second state appointment, the reality is that other tenderers may have lost interest in the project, and the embedded contractor will have a significant competitive advantage.
The earlier the contractor is appointed, the greater the potential benefits they are able to bring to the project, but the less able they are to provide accurate pricing information for the second-stage tender process. Also, the second stage is likely to be.less competitive.
[edit] Related articles on Designing Buildings Wiki
- Adversarial behaviour in the UK construction industry.
- Appointing consultants.
- Civil Engineering Procedure.
- Construction contract.
- Construction management.
- Contracting.
- Design and build.
- Design and manage procurement route.
- Early appointment / involvement.
- Integrated project team.
- Management contract.
- NEC early contractor involvement.
- Open book accounting.
- Optimised contractor involvement.
- Pre-construction services agreement.
- Procurement route.
- Single-stage tender.
- Tender.
- Tender processes.
- Two stage open book.
- Two stage tender.
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.