Pre-construction phase
The term ‘construction’ refers to the process of building something such as a house, bridge, tunnel, and so on.
Construction projects are typically divided up into stages, at the end of which the client assesses the state of development of the project and considers; whether it satisfies their strategic objectives, that it is affordable, that value is being delivered, and that risks are acceptable. They can then decide whether to progress to the next stage.
A typical project might follow stages such as:
- Stage 1: Business justification.
- Stage 2: Feasibility studies.
- Stage 3: Project brief.
- Stage 4: Concept design.
- Stage 5: Detailed design.
- Stage 6: Production information.
- Stage 7: Tender.
- Stage 8: Mobilisation.
- Stage 9: Construction.
- Stage 10: Occupation and defects liability period.
- Stage 11: Post occupancy evaluation.
Typically, the construction phase consists of carrying out the construction works described in the contract and preparing for the client to occupy the works.
The pre-construction works, in their broadest sense, might include any activities before the construction phase commences, such as; business planning, appointing consultants, the preparation of feasibility studies and options appraisals, preparing the project brief, designing the project, obtaining permissions, appointing a contractor, preparing for construction to commence and so on.
However, a specific legal meaning of “pre-construction phase” exists in relation to health and safety. The Construction (Design and Management) Regulations (CDM Regulations) are intended to ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced. They were introduced in 1994 following publication of European Directive 92/57/EEC on minimum safety and health standards for temporary or mobile construction sites.
The CDM Regulations 2015 suggests that the construction phase means the period of time beginning when construction work in a project starts and ending when construction work in that project is completed. The pre-construction phase refers to any period of time during which design or preparatory work is carried out for a project and may continue during the construction phase.
This might include:
- Appointing duty holders.
- Ensuring risks are eliminated or controlled through design work.
- Passing information to the principal contractor.
- Ensuring cooperation and coordination.
- Ensuring designers comply with their duties.
- Preparing pre-construction information.
For more information see: CDM 20215.
These activities may continue after the construction phase has commenced, as the design may continue to develop and so health and safety considerations may change.
NB Using Two Stage Open Book and Supply Chain Collaboration, published by HMSO in 2014, defines the preconstruction phase as: ‘…the phase of a project or programme of work before the Client authorises commencement of all works and related activities on and off site.’ It defines a preconstruction phase timetable as: ‘…a contractually binding timetable governing deadlines and interfaces for Preconstruction Phase activities by Integrated Team members under a Conditional Contract.’
[edit] Related articles on Designing Buildings
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.