Pre-construction phase
The term ‘construction’ refers to the process of building something such as a house, bridge, tunnel, and so on.
Construction projects are typically divided up into stages, at the end of which the client assesses the state of development of the project and considers; whether it satisfies their strategic objectives, that it is affordable, that value is being delivered, and that risks are acceptable. They can then decide whether to progress to the next stage.
A typical project might follow stages such as:
- Stage 1: Business justification.
- Stage 2: Feasibility studies.
- Stage 3: Project brief.
- Stage 4: Concept design.
- Stage 5: Detailed design.
- Stage 6: Production information.
- Stage 7: Tender.
- Stage 8: Mobilisation.
- Stage 9: Construction.
- Stage 10: Occupation and defects liability period.
- Stage 11: Post occupancy evaluation.
Typically, the construction phase consists of carrying out the construction works described in the contract and preparing for the client to occupy the works.
The pre-construction works, in their broadest sense, might include any activities before the construction phase commences, such as; business planning, appointing consultants, the preparation of feasibility studies and options appraisals, preparing the project brief, designing the project, obtaining permissions, appointing a contractor, preparing for construction to commence and so on.
However, a specific legal meaning of “pre-construction phase” exists in relation to health and safety. The Construction (Design and Management) Regulations (CDM Regulations) are intended to ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced. They were introduced in 1994 following publication of European Directive 92/57/EEC on minimum safety and health standards for temporary or mobile construction sites.
The CDM Regulations 2015 suggests that the construction phase means the period of time beginning when construction work in a project starts and ending when construction work in that project is completed. The pre-construction phase refers to any period of time during which design or preparatory work is carried out for a project and may continue during the construction phase.
This might include:
- Appointing duty holders.
- Ensuring risks are eliminated or controlled through design work.
- Passing information to the principal contractor.
- Ensuring cooperation and coordination.
- Ensuring designers comply with their duties.
- Preparing pre-construction information.
For more information see: CDM 20215.
These activities may continue after the construction phase has commenced, as the design may continue to develop and so health and safety considerations may change.
NB Using Two Stage Open Book and Supply Chain Collaboration, published by HMSO in 2014, defines the preconstruction phase as: ‘…the phase of a project or programme of work before the Client authorises commencement of all works and related activities on and off site.’ It defines a preconstruction phase timetable as: ‘…a contractually binding timetable governing deadlines and interfaces for Preconstruction Phase activities by Integrated Team members under a Conditional Contract.’
[edit] Related articles on Designing Buildings
Featured articles and news
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.




















