Engineering Recommendation G99
Contents |
[edit] Introduction
Engineering Recommendation G99, or EREC G99, was issued by the Energy Networks Association (ENA) in July 2018 and came into effect on 27 April 2019. It applies to organisations involved in developing generation projects that are connected to the grid. It also affects how different types or configurations of equipment must comply with the requirements.
EREC G99 was published by the ENA to replace EREC G59. After 27 April 2019, organisations were longer legally permitted to connect certain types of power generation equipment that was solely compliant with G59.
[edit] Changes brought about by EREC 99
EREC 99 established more stringent operating parameters for all new generation equipment 1MW (or larger) that would be connected to public distribution networks of licensed Distribution Network Operators (DNOs). It also changed the application process for this type of equipment and put new compliance and commissioning requirements in place.
Under EREC G99, this type of equipment must provide frequency response in either Limited Frequency Sensitive Mode (LFSM) or Frequency Sensitive Mode (FSM) to control active power output in response to frequency changes on the grid.
Generators over 1MW must also include:
- Fault ride through to keep them connected when there are significant voltage depressions due to faults on the grid.
- Fast fault current injection to support the system during a fault by quickly injecting reactive current in order to keep the grid voltage from dropping too low.
- Voltage control systems that can inject or absorb reactive power into the grid to control voltage.
- Enhanced variable reactive power capabilities.
- Testing and protection capabilities previously handled by large grid code compliant power stations.
[edit] Related articles on Designing Buildings
- Microgeneration for buildings
- Power generation
- Power supply.
- Smoothing the path to net zero.
- The future of UK power generation.
[edit] External resources
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.