Engineering Recommendation G99
Contents |
[edit] Introduction
Engineering Recommendation G99, or EREC G99, was issued by the Energy Networks Association (ENA) in July 2018 and came into effect on 27 April 2019. It applies to organisations involved in developing generation projects that are connected to the grid. It also affects how different types or configurations of equipment must comply with the requirements.
EREC G99 was published by the ENA to replace EREC G59. After 27 April 2019, organisations were longer legally permitted to connect certain types of power generation equipment that was solely compliant with G59.
[edit] Changes brought about by EREC 99
EREC 99 established more stringent operating parameters for all new generation equipment 1MW (or larger) that would be connected to public distribution networks of licensed Distribution Network Operators (DNOs). It also changed the application process for this type of equipment and put new compliance and commissioning requirements in place.
Under EREC G99, this type of equipment must provide frequency response in either Limited Frequency Sensitive Mode (LFSM) or Frequency Sensitive Mode (FSM) to control active power output in response to frequency changes on the grid.
Generators over 1MW must also include:
- Fault ride through to keep them connected when there are significant voltage depressions due to faults on the grid.
- Fast fault current injection to support the system during a fault by quickly injecting reactive current in order to keep the grid voltage from dropping too low.
- Voltage control systems that can inject or absorb reactive power into the grid to control voltage.
- Enhanced variable reactive power capabilities.
- Testing and protection capabilities previously handled by large grid code compliant power stations.
[edit] Related articles on Designing Buildings
- Microgeneration for buildings
- Power generation
- Power supply.
- Smoothing the path to net zero.
- The future of UK power generation.
[edit] External resources
Featured articles and news
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.