Cost overruns in construction
In construction, cost overruns are relatively common, occurring when the costs being incurred are in excess of the amounts that have been budgeted for.
There are a number of possible reasons for this:
- Construction contracts are often tendered and won on the basis of the lowest cost bid. Costs can then increase as contractors attempt to claw back some profit.
- Construction projects are complex, involving a large number of different parties, components, requirements and other factors.
- Projects can take a long time to complete, during which costs may change.
- Deficiencies and inaccuracies in design.
- Poor project management.
- Changes in client requirements.
- Unforeseen costs that only become apparent as the works progress.
- Poor communication between project team members.
- Tools, equipment and plant being unavailable, in poor condition, etc.
- Skilled workers being unavailable.
- Inaccurate cost information that leads to incorrect pricing (e.g. material prices).
- Adverse site or ground conditions.
- Late or withheld payments.
- Scope creep.
The different ways in which cost overrun can be described include:
- As a percentage of the total cost.
- As a total percentage including the original budget and the overrun amount.
- As a percentage of the cost overruns to the original budget.
In order to address and manage cost overruns, it is important to identify what the root causes are. While specific events such as extreme weather conditions can cause delays or damage which may result in cost overruns, they are often the result of more complex project management issues that can be difficult to untangle.
The largest cost overruns tend to occur due to a change in requirements. If, for example, the client needs a space to be 20% larger than originally anticipated, then the cost is likely to increase by at least 20%. It is very important therefore to ensure that the project brief is comprehensive and that all project stakeholders accept it and agree on the specific scope of work and performance requirements.
Pre-construction estimates and careful project planning are then vital in terms of ensuring accuracy and confidence in the project costings, particularly if the project is complex and has the potential to change.
Design and construction issues can be mitigated in some cases by using project-wide project management, cost control software or building information modelling (BIM) as a way of ensuring all stakeholders are using the same up-to-date design information, as well as being able to make real-time adjustments.
Change orders may also be a reason for costs overrunning. A change order is work that is added to or deleted from the original scope of work of a contract, which alters the original contract amount and/or completion date.
If one of the parties to a contract fails to perform as required by the contract, and this results in costs overrunning, it may constitute a breach of contract. A breach of contract may entitle the innocent party to make a claim for damages for the losses it has suffered.
Construction contracts will generally provide for the contractor to claim direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Starting pistol Statement for an election campaign?
Rates freeze, NI cuts, full expensing; early election?
Positive pressure or positive input ventilation
Could this be a remedy for condensation, damp or mould?
Unlocking a Healthier Tomorrow
Report on Social housing retrofit in Scotland 2023
Call for ministerial group and National Retrofit Delivery Plan.
The Great Transformation 1860–1920. Book review.
2023 Autumn Statement in brief with reactions
Including the devolved governments, CIOB, ECA, APM and IHBC.
Irish Life Sciences HQ, an exemplar of adaptive reuse
AT awards small to medium size project category winner.
Formal and informal adaptive re-use or new use of buildings.
Broken Record. Emissions Gap Report 2023
Temperatures hit new highs, yet world fails to cut emissions (again).
Environment Agency cuts waste red tape
No longer enforcing certain waste transfer documentation.
APM Project Management Awards 2023
Winners reactions during the event at the Park Plaza Hotel.
BSRIA Living Laboratory Innovation Challenge
An exciting opportunity for stakeholders to collaborate.
Discussing issues related to inside and outside air quality
Report from the BSRIA Briefing 2023, Cleaner Air, Better Tomorrow.
Education and Health applications shine in October
Within a somewhat subdued construction market.
Restoring the Odisha East Coast Canal
A lifeline to the communities along its length.
Bill to tackle lithium-ion batteries proposed
Led by Electrical Safety First and supported by ECA.