Cost overruns in construction
In construction, cost overruns are relatively common, occurring when the costs being incurred are in excess of the amounts that have been budgeted for.
There are a number of possible reasons for this:
- Construction contracts are often tendered and won on the basis of the lowest cost bid. Costs can then increase as contractors attempt to claw back some profit.
- Construction projects are complex, involving a large number of different parties, components, requirements and other factors.
- Projects can take a long time to complete, during which costs may change.
- Deficiencies and inaccuracies in design.
- Poor project management.
- Changes in client requirements.
- Unforeseen costs that only become apparent as the works progress.
- Poor communication between project team members.
- Tools, equipment and plant being unavailable, in poor condition, etc.
- Skilled workers being unavailable.
- Inaccurate cost information that leads to incorrect pricing (e.g. material prices).
- Adverse site or ground conditions.
- Late or withheld payments.
- Scope creep.
The different ways in which cost overrun can be described include:
- As a percentage of the total cost.
- As a total percentage including the original budget and the overrun amount.
- As a percentage of the cost overruns to the original budget.
In order to address and manage cost overruns, it is important to identify what the root causes are. While specific events such as extreme weather conditions can cause delays or damage which may result in cost overruns, they are often the result of more complex project management issues that can be difficult to untangle.
The largest cost overruns tend to occur due to a change in requirements. If, for example, the client needs a space to be 20% larger than originally anticipated, then the cost is likely to increase by at least 20%. It is very important therefore to ensure that the project brief is comprehensive and that all project stakeholders accept it and agree on the specific scope of work and performance requirements.
Pre-construction estimates and careful project planning are then vital in terms of ensuring accuracy and confidence in the project costings, particularly if the project is complex and has the potential to change.
Design and construction issues can be mitigated in some cases by using project-wide project management, cost control software or building information modelling (BIM) as a way of ensuring all stakeholders are using the same up-to-date design information, as well as being able to make real-time adjustments.
Change orders may also be a reason for costs overrunning. A change order is work that is added to or deleted from the original scope of work of a contract, which alters the original contract amount and/or completion date.
If one of the parties to a contract fails to perform as required by the contract, and this results in costs overrunning, it may constitute a breach of contract. A breach of contract may entitle the innocent party to make a claim for damages for the losses it has suffered.
Construction contracts will generally provide for the contractor to claim direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.


























