Competitive tender
Competitive tendering is a common method of procurement in the construction industry.
A tender is a submission made by a prospective supplier/contractor in response to an invitation to tender. It makes an offer for the supply of goods or services.
Those tendering for a contract are often competing with others, and generally, none of the tenderers are aware of the quotes provided by each other; therefore, they are incentivised to submit their most competitive tender. In this way, it is believed that competition in procurement can add value for the client.
Competitive tendering became increasingly common in the UK in the 1980s, when it was seen as a way of making public organisations open themselves up to bids from a number of different firms. This was intended to increase transparency, drive down costs, and improve the efficiency of state-funded organisations such as central and local government departments.
However, it has been criticised for placing too much emphasis on cost, and not necessarily achieving best value for the client. Competitive tendering can be seen as a 'race to the bottom' and can lead to disputes later in the project as suppliers seek mechanisms to increase their price.
Methods of assessing tenders which consider criteria other than the lowest cost include:
- Best value.
- Auction theory.
- Most Economically Advantageous Tender (MEAT).
- Mean value.
- Exclusion of the extremes.
- Weighted selection criteria.
- Balanced scorecard.
For more information see: Tender evaluation, and Procurement route.
NB The UN Procurement Practitioner's Handbook, produced by the Interagency Procurement Working Group (IAPWG) in 2006 and updated in 2012, defines competitive bidding as: 'A procurement method in which offers from competing suppliers are invited by open advertisement and provided with the scope, specifications, and terms and conditions of the proposed contract as well as the criteria by which the offers will be evaluated. The objectives of competitive bidding are to obtain goods or services at the lowest cost or best value through open and fair competition.'
[edit] Related articles on Designing Buildings Wiki
- Best value.
- Best value procurement.
- Bid evaluation.
- Bid strategies.
- Compliant bid.
- Form of tender.
- Insourcing.
- Most economically advantageous tender (MEAT).
- Non-compliant tender.
- Preferred tenderer.
- Proposals.
- Single-stage tender.
- Tender.
- Tender evaluation.
- Two-stage tender.
- Variant bid.
- Why the lowest price isn't sustainable.
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Guide to ISO 19650 for Architecture Firms (2026)
A user gives their low down.
A UK training and membership provider for mould remediation professionals.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
Independent NSI and BAFE study exploring how organisations are changing the way they buy fire safety services.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.