Commencement of construction works
In very broad terms, the word ‘commencement’ means beginning something. In the construction industry this generally refers to the contractor beginning the construction works, ie the point at which site clearance, demolition, excavation or construction begins. For more information see: Construction operations definition.
Commencement of construction works will be proceeded by activities such as design, procurement and mobilisation, and there may be legal requirements that need to be satisfied, such as obtaining planning permission, satisfying planning conditions or planning obligations, obtaining building regulations approval, obtaining a party wall agreement, notifying the Health and Safety Executive and so on. For more information see: What approvals are needed before construction begins.
In addition, commencement may be required before a certain point, for example, within 3 years of the date planning permission was granted, or within three years from the date of deposit of plans for building regulations approval.
Commencement may also have contractual implications, as the date for possession of the site by the contractor may be set out in the contract. If the client fails to give possession of the site to the contractor, and there are no provisions for delay in the contract, then they will be in breach of contract. Even if the contract does provide for delay in giving possession of the site to the contractor, the contractor may still be able to claim for an extension of time and perhaps loss and expense.
If no date for possession is included in the contract, then the site must be handed over to the contractor within a reasonable time after signing of the contract.
On commencement of the works, the contractor may become responsible for insurance, security of the site and so on, and may be obliged to progress regularly and diligently with the works, or to achieve certain key dates.
The term ‘commencement’ might also be used to refer to the commencement of an appointment, the commencement of a contract, commencement of legal proceedings and so on.
NB There is currently no legal UK definition of (as opposed to guidance on) "commencement" for the purposes of the building regulations. Knowing whether work has commenced will be critical to understanding whether approval has lapsed and/or whether work benefits from transitional provisions. Consequently, a legal definition of "commencement" is being considered.
[edit] Related articles on Designing Buildings
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.





















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.